At OC Transpo, we are dedicated to providing up-to-date and factual information and data. Our commitment to transparency is part of being accountable for providing safe, comfortable and reliable transit services. It also ensures that you, our customers and stakeholders, have confidence in the system.
As part of ongoing initiatives to improve our communications with customers, we have enhanced information available on performance and management of our services and programs.
OC Transpo provides regular updates to Ottawa City Council and the Transit Commission regarding transit service improvements, projects, and initiatives, and significant issues affecting customers, among other topics.
To: Mayor and Members of Council
From: Michael Morgan, Director, Rail Construction Program, Transit Services Department
The following memo outlines the progress made during Q1 2023 on the Stage 2 project and provides an overview of the planned work for Q2 2023.
The City has been working closely with TransitNEXT to advance critical works that would enable the handover of the system to the City this year. Based on the current review of all inputs including an agreement on the training requirements, the current working timeline for the project handover is the beginning of October.
Subsequent to project handover, the City will make an assessment regarding the timing for start of public service. Final readiness activities and an assessment of system maturity will be made after handover from the build team.
Note that this timeline is based on the information we have available and assumes that completion of remaining milestones will be relatively smooth. There remains some risk and uncertainty in the completion of the remaining works.
The achievement of the handover milestone is contingent upon:
Staff worked with TransitNEXT in Q1 2023 to continue resolving open comments for stations, guideways, and maintenance facilities. Staff reviewed issues for construction drawings for the Hunt Club Rail Bridge and the final design submissions for the communication systems.
Final signage and wayfinding shop drawings for the stations and Walkley Maintenance and Storage Facility (MSF) have also been submitted by TransitNEXT for a final accuracy review by Transit Services.
During Q1 2023, the construction of all 13 Trillium Line stations continued, including elevator installation, platform work, utilities work, aluminum composite panels (ACM) and shelter installation, painting, glazing installation, communications cable pulling, mechanical, electrical and plumbing work. The main breaker at Corso Italia, Carleton, Greenboro and Airport stations were energized during this period.
Work progressed in the Dow’s Lake Tunnel and pump house with cable pulling and termination of jet fan electrical connections.
Works progressed at the new Walkley Yard Facility (MSF), including epoxy flooring installation, commissioning of the HVAC system and various equipment that will be used on the trains. Work progressed in the train wash building with the installation of the energy recovery unit, floor grating and overhead doors. The train wash building was energized on permanent power during Q1 2023. Electrical, mechanical and HVAC rough-in scope also progressed at the inspection building.
Trackwork progressed along the entire alignment including track welding, destressing, and surfacing. Special trackwork installation continued at the Bayview and Limebank cross-over, and turnouts were also installed at various sections of the alignment. Direct fixation (DF) track installation started during Q1 2023 at Ellwood and Airport elevated guideways.
Hunt Club bridge works continued in Q1 2023 with the barrier walls between the rail and pathway completed, median barrier wall started, and remaining bridge approach work progressed during Q1 2023. Bridge works on the elevated guideway at Ellwood and the airport are nearing completion.
Following the completion of construction and then testing and commissioning program, TransitNEXT will begin a three-week trial running period to validate that all aspects of the system and maintenance activities perform as expected.
Following the successful completion of Trial Running as well as completion of all PA requirements, Substantial Completion will be achieved.
The system will then be available for OC Transpo to complete any remaining operational readiness activities before determining a final opening date to the public. The duration of this final process for validation of system readiness is still to be determined.
The East extension is currently forecasting a completion date of January 16, 2025, which is an approximate 7-week delay from the Project Agreement (PA) completion date of November 26, 2024 – this is a slight reduction from previous reports.
On the West extension, from Tunney’s Pasture Station to Moodie and Algonquin stations, the City is expecting a delay of up to 17 months against the contractual completion date of May 25, 2025. Specific elements such as the light maintenance and storage facility (LMSF) and Lincoln Fields Station are progressing well. Production rates and accumulated delays on the Cut and Cover Tunnel along the Sir John A. Macdonald Parkway and Byron Linear Park are pushing the overall project completion date to late 2026.
Note that the project has two independent opening dates, with the eastern extension segment, from Blair Station to Trim Station, planned to open first.
In Q1 2023, City staff continued their review of EWC’s designs of specific Confederation Line extension elements, including stations. The focus is now on closing open comments on design packages. In Q1 2023, staff continued the review of design documents for stations and remaining roads packages.
The review of other works that will be completed following Substantial Completion, including the Richmond Road Complete Streets and the decommissioning of portions of the Transitway, will continue in Q2 2023.
There is now a focus on review of testing and commissioning plans and documents that are now being provided by EWC.
Bulk excavation in the existing transitway trench between Kìchì Sìbì and Tunney’s Pasture stations progressed in Q1 2023 and is now complete for this area. Drainage work and rehabilitation of the trench walls including scaling and installation of anchors, shotcrete, and drapery continues in the trench.
Rail and rail tie delivery to the LMSF started in Q4 2022, and rail welding and installation began in Q1 2023. Energization of the TPSS building at the LSMF is complete. Catenary poles and catenary work are expected following installation of rail this spring.
In the east, the majority of the 23-kilometre guideway barrier wall between the rail guideway and the highway has been completed.
Overhead Catenary System (OCS) pole and cable trough installation continued, and the majority has been completed from Blair to Jeanne d’Arc stations. The Majority of OCS poles’ cantilever arms have been installed between the Blair flyover and Jeanne d’Arc Station as well.
Track installation between Blair and Jeanne d’Arc stations is complete. Track installation between Trim and Place d’Orléans stations continues and is progressing well. Trackwork between Jeanne d’Arc and Place d’Orléans stations is expected to begin in Q2 2023.
The TPSS units for Montréal and Place d’Orléans stations have been delivered and installed. The remaining three TPSS units in the East will be delivered in Q2 2023. Racks and cabinet installation as well as cable pulling started in the Train Signal equipment rooms in the East stations and will continue in Q2 2023.
Finishing works at Montréal and Jeanne d’Arc stations continues. Footings and foundation walls work at Convent Glen Station were completed in Q1 2023, underground mechanical and electrical, slab-on-grade and steel erection work will continue in Q2 2023. Framing and sheet rock work continued at Place d’Orléans Station. The concourse level pour has been completed at Trim Station. Escalators were delivered and installed at Place d’Orléans and Trim stations.
The handover sequence for the Stage 2 Confederation Line is different than in Stage 1. Following completion of the infrastructure and system commissioning by EWC, a three-week trial running period involving City operations, Rideau Transit Group and Rideau Transit Maintenance and EWC will be completed to verify operation and maintenance of the completed system. Following this work, additional time may be used for trial operations prior to opening for passenger service.
RTG is providing 38 additional Alstom Citadis Spirit light rail vehicles to ensure that the expanded Stage 2 Confederation Line operates as a single, uniform service. To date, 10 Stage 2 vehicles have been accepted and are in use as part of the operating fleet.
Configuration updates, software change, reliability and performance modifications that have been identified through Line 1 service since 2019, are being applied to the Stage 1 vehicles and to the Stage 2 vehicles in order to create a homogeneous fleet. Additional vehicles are undergoing final commissioning now and the fleet size is expected to be sufficient for the east extension by the end of this year. The remaining fleet order is expected to arrive well ahead of the west extension timelines.
TransitNEXT will supply seven Stadler FLIRT vehicles for the expanded Trillium Line, which have already been delivered to Ottawa. The existing Alstom LINT fleet have undergone a retrofit program and are now ready for systemwide testing and commissioning.
The Stage 1 Confederation Line contingency fund is $115 million. To date, $100.03 million from the total fund has been spent. Remaining funds are primarily related to property requirements and remaining commercial matters.
The original Stage 2 contingency fund of approximately $152 million was increased by $25 million due to unforeseen costs and improvements to the project, as approved by Council on July 6, 2022. Approximately $166 million of the Stage 2 contingency fund has been committed to date. Additional pressures remain on the contingency due to project delays increasing the cost for City oversight, existing and emerging variations for system improvements, residual project risks over the remainder of the project life, and open commercial issues.
In keeping with Council’s approved 2017 Stage 2 Report (ACS2017- TSD-OTP-0001) and 2019 Stage 2 Report (ACS2019-TSD-OTP-0001), approximately $3.019 billion has been spent as of March 31, 2023 and relates to the RTG MOU for Belfast Yard and vehicle assembly mobilization ($424M), Confederation Line extension mobilization and construction period payments ($1.537B), Trillium Line extension construction period payments and financial close for the Revenue Vehicle Supply Contract ($602M), and contingency ($61M). The remaining $395M was spent for planning, procurement, project delivery and City retained scope.
Notably, the City received the final $60M payment from the MTO for Stage 1 on March 15, 2023 and received the final $60M payment from Transport Canada for Stage 1 in two installments, $5.8M on April 12, 2023 and $54.2M on April 18, 2023. No funds are outstanding and the funding agreements for Stage 1 of the Confederation Line are now closed. The City will continue to report on critical reliability issues on the Confederation Line to the funding partners as part of the Stage 2 funding agreement.
Project Description |
Authority |
Actual Expenditures |
Funds Reserved/Committed |
Unspent/Uncommitted |
---|---|---|---|---|
Stage 1 |
||||
Confederation Line Program |
2,130,000,000 |
2,130,000,000 |
- |
- |
Contingency |
15,000,000 |
100,026,391 |
14,973,609 |
- |
Total Stage 1 |
2,245,000,000 |
2,230,026,391 |
14,973,609 |
- |
Stage 2 |
||||
Confederation Line Extensions DBF Contract |
2,680,832,113 |
1,536,991,384 |
1,143,840,728 |
- |
Trillium Line Extension DBFM Contract |
810,159,585 |
601,609,174 |
70,028,421 |
- |
Deferred Equity (Maintenance Term) |
- |
- |
138,521,990 |
- |
RTG Stage 2 MOU (includes 38 Alstom vehicles) |
516,184,423 |
424,310,870 |
91,795,352 |
78,201 |
City Costs (includes planning, procurement, property acquisitions, City retained scope, and delivery oversight) |
532,629,108 |
394,337,767 |
40,778,625 |
97,512,715 |
Contingency |
177,640,000 |
61,307,396 |
105,008,910 |
11,323,694 |
Total Stage 2 |
4,717,445,229 |
3,018,556,592 |
1,589,974,026 |
108,914,610 |
In Q1 2023, the Stage 2 LRT communications highlights include:
On March 29, the LRT Sub-Committee received an update on the Stage 2 project. There is significant progress being made in the East, West and South that residents can see in this video and read about in this blog story.
Residents are encouraged to subscribe to the Stage 2 LRT newsletter and follow Stage 2 on Instagram @Stage2Etape2 to receive progress updates, construction photos and videos and area specific notifications regarding upcoming works. Residents can also subscribe to the electronic newsletters by visiting ottawa.ca/Stage2Connect.
Should you have any questions about the information provided in this memo, please do not hesitate to contact me at extension 52718.
Original signed by
Michael Morgan
c.c. Senior Leadership Team
Transit Services Departmental Leadership Team
Director, Public Information and Media Relations
To: Mayor and Members of Council
From: Renée Amilcar, General Manager, Transit Services Department
The purpose of this memo is to provide Mayor and Members of Council with information on changes to OC Transpo’s Twitter accounts that are designed to support customers.
OC Transpo began using Twitter in 2010; it has since gained close to 82,000 followers and shared almost 400,000 updates across three accounts. In that time, social media has significantly evolved, as have customer expectations.
As part of OC Transpo’s commitment to implementing industry best practices, increasing responsiveness to customer inquiries, improving overall communications, and building public trust, OC Transpo is relaunching its Twitter accounts.
Starting today, “OC_TranspoHelps” and “OC_TranspoAide” are replacing the “OCTranspoLive” and “OCTranspoDirect” accounts. These new customer service-focused Twitter accounts are managed by customer service representatives who are empowered to quickly respond to customer inquiries and provide support.
Detours, major disruptions, and other important service alerts will continue to be shared on these accounts. This complements OC Transpo’s organizational account, “OC_Transpo”, which provides system-wide updates and general information for customers, such as links to the Next Stop Blog posts.
While some customers may have used the previous Twitter accounts to find changes to their specific bus trips, this is no longer possible. Twitter has introduced new pricing to access certain features of their platform, which would add a cost of approximately $675,600 per year to continue to post specific trip information.
This update to OC Transpo’s Twitter presence is also a component of a plan to improve communications with customers; further enhancements can be expected. These improvements will complement ongoing work to upgrade real-time data information for customers. Additional information on the real-time data project will be provided at the May 11 Transit Commission meeting.
Customers can continue to find specific bus trip information, like bus departure times, by:
OC Transpo will be communicating with customers on our channels to inform them of this change.
We would be grateful for your assistance in communicating this change to residents. Attached are some sample social media posts to assist in sharing this information.
Should you have any questions or comments, please contact, Lisa Bishop-Spencer, Director Transit Strategic Communications and External Relations, at extension 51266, or me at ext. 52111.
Original signed by,
Renée Amilcar
c.c.: Senior Leadership Team
Transit Services Departmental Leadership Team
Director, Public Information and Media Relations
To: Mayor and Members of Council
Chair and Members of the Transit Commission
From: General Manager, Transit Services Department
The purpose of this memo is to provide Members of Council and the Transit Commission with an update regarding the temporary scaffolding located at Tunney’s Pasture and Hurdman stations. This scaffolding was installed in late 2019 to provide additional weather protection for customers along some sections of the bus platforms.
As directed by City Council at its meeting of March 1, 2023, the temporary scaffolding will be removed in May. At Tunney’s Pasture Station, the work will start as early as May 1, and is expected to take up to 14 days. At Hurdman Station, the work will start as early as May 11, and will last up to 10 days. The work will take place overnight, between 9 p.m. and 5 a.m. and will not result in impacts for customers at the stations.
As directed by Council, staff are preparing a proposal, including a cost breakdown, of potential permanent solutions for both Tunney’s Pasture and Hurdman stations. Staff are examining the feasibility and cost of installing permanent improved weather protection for Hurdman Station and the south-side bus platforms at Tunney’s Pasture Station, which will remain in use after the opening of the Stage 2 extensions. In addition, staff are also examining interim improved weather protection for the north-side bus platforms at Tunney’s Pasture Station, which are to be removed from service following the Stage 2 west extension.
Staff will assess what work is feasible within the current capital authority and what work would require additional funding authority for consideration through the future capital budget process. The proposal will be presented to the Transit Commission once it is complete, and in advance of the 2024 budget discussions.
Should you have any questions or comments, please contact Scott Laberge, Associate Director, Transit Customer Systems and Planning at ext. 14120, or me at ext. 52111.
Original signed by
Renée Amilcar
cc: Senior Leadership Team
Transit Services Departmental Leadership Team
Director, Public Information and Media Relations
To: Mayor and Members of Council
From: General Manager, Transit Services Department
The purpose of this memo is to advise the Mayor and Members of Council that new convenient ways for customers to pay their fares on Para Transpo are now available. As mentioned at the Transit Commission meeting on April 13, all Para Transpo minibuses and taxis now have smartcard readers installed, providing customers with more options to pay for their fare, including a Presto card, a credit card, or a credit card in a mobile wallet on a smartphone.
Adding smartcard readers to Para Transpo vehicles simplifies the customer experience, as customers no longer need to provide a receipt as proof of payment. Customers can simply buy a Presto card, register it at prestocard.ca, add their monthly pass or load funds to their e-Purse, and use the card to pay for their fare when they board.
Payment by credit card will always charge a full Adult fare. The option to pay with a debit card will also be introduced soon, and customers continue to have the option to pay for their trips with cash or their ParaPay account.
Customers with existing discounts on their ParaPay accounts can call 613-560-5000 to have their discount transferred to a Presto card. Age-based discounts including Senior discounts can be added to a card in person at participating Shoppers Drug Mart, Loblaws and Real Canadian Superstore locations or at the OC Transpo Customer Service Centre at the Rideau Centre.
Information will be communicated to customers through OC Transpo’s information channels, including a public service announcement, printed material, social media updates, and octranspo.com.
Should you have any questions or comments about any of the points in this memo, please contact Pat Scrimgeour, Director, Transit Customer Systems and Planning, at extension 52205.
Original signed by
Renée Amilcar
cc: Senior Leadership Team
Transit Services Departmental Leadership Team
Director, Public Information and Media Relations
To: Mayor and Members of Council
From: Director, Rail Construction Program
The following memorandum provides Mayor and Council with information regarding appointments to the Stage 2 Confederation Line Project extensions in the east and west of the city to support the delivery and startup of the project, and provides additional information in advance of the technical briefing scheduled for April 19, 2023 at 2 p.m. A previous iteration of this memorandum (also attached for reference) provided details on the oversight appointments on the Stage 2 Trillium Line extension.
As a starting point, it is worth noting that there are significant differences between the startup of a new rail line, such as in Stage 1 of the Confederation Line, and the work to extend an operational railway as with the Stage 2 project. For a new startup, testing activities are completed in a closed environment and the work is generally isolated from end users. For an extension project, the work can be completed in a closed environment to begin with but, eventually, requires integration and testing of the interfaces between the new sections and the existing section. The availability of existing infrastructure and vehicles helps to simplify testing of some elements of an extension project but also creates additional complexities at the boundary between the new infrastructure and the existing infrastructure. The various oversight roles described below have been organized to match the complexity of the Stage 2 program.
These appointments address Recommendation #28 from the Ottawa Light Rail Public Inquiry related to oversight, systems integration, and independent certification of the new rail lines.
Stage 2 Systems Integration
As noted in previous updates to Council, the Stage 2 Confederation Line Project Agreement (PA) adopts lessons learned from Stage 1 and uses a different strategy for dealing with systems integration and verification of project requirements.
The Confederation Line PA requires that East West Connectors (EWC) undertake a robust approach to systems engineering and integration activities based on a systems engineering approach defined by European Standards EN 50126 and ISO/IEC/IEEE 15288:2015 standards.
These standards establish a defined framework for the implementation of systems engineering and integration activities within project life cycle stages. Simply put, the framework defines what systems engineering and integration activities need to take place during each project phase using a regimented engineering management approach. This process ensures that the necessary interfaces and interactions between the different project components, including infrastructure, facilities, subsystems, software, operations, and maintenance, have been identified and engineered to function together as a holistic system. The application of these standards will support these interdependent systems coming together to form a safe and reliable transit service.
To assist with these activities, the City and EWC have jointly engaged a System Integration Verifier (SIV) who will assist the parties in confirming the system integration requirements as between the City’s work on the Transit Operations Control Centre and the connections to field equipment provided by EWC. The SIV is a third-party independent function that provides verification services to both the City and EWC as part of the Stage 2 systems integration works. The role of the SIV is to monitor critical system implementation and integration milestones and certify that the testing has validated their successful implementation.
The Stage 2 SIV contract has been awarded to Ingerop, an international French multi-disciplinary engineering firm, with over 2,300 employees and 50 branches worldwide. Areas of specialization cover transport systems integration, signaling and CBTC, catenary and other railway systems. Ingerop has been involved with LRT and Metro projects worldwide, including Line 15-SouthGrand Paris (France) Metro, Line 18 GrandParis Metro, T9 Paris tramway, Line 1and 3 Lima Metro (Perú), L3 Seville Metro (Spain), Granada LRT (Spain), Málaga Metro (Spain), Zaragoza LRT (Spain), Madrid ML1, ML2 and ML3LRT projects (Spain), Medellín tramway (Colombia) and Line 1 Mexico DB (Mexico).
The Stage 2 Confederation Line Project Agreement also requires that KEV (Kiewit, Eurovia, and Vinci) undertake a vigorous system safety assurance process to certify that all elements of the new expanded system are safe prior to the start of revenue operations. KEV’s system safety and assurance process is guided by European Standards EN 50126 which defines Reliability, Availability, Maintainability and Safety (RAMS) activities during each project phase. This iterative approach to system safety and assurance – leading to a Safety Case compliant with the European Standard EN 50129 - ensures that KEV is regularly reviewing, defining, and improving upon its safety tasks during each project phase. These standards establish a defined framework for the implementation of systems integration activities within project life cycle stages. Simply put, the framework defines what systems integration activities need to take place during each project phase using a regimented project management approach. As part of the Project Agreement, KEV is required to provide a Systems Integration Manager with at least 15 years’ experience in this area to manage this scope.
Stage 2 Independent Oversight
The City is overseeing all aspects of the safety certification process through a joint team of City staff, external specialist consultants, and an independent safety auditor. The auditor will confirm that KEV’s approach to system safety and assurance is sound, and that it has fulfilled compliance with all safety requirements throughout each project phase. The City has engaged SENER Inc. as the safety auditor, an international engineering and technology firm with wide experience in safety auditing and acceptance services. SENER is a certified Railway Independent Safety Auditor (ISA) that has provided ISA services throughout the world, including metro line 9 to the Barcelona International Airport (Spain), the Zapopan to Guadalajara and Tlaquepaque LRT system (Mexico), and the Lusail LRT Tramway (Qatar).
As is the standard model for this type of project, an Independent Certifier (IC) has been engaged to actively review the progress of works on site and authorize payments for works completed. The IC assigned to the Stage 2 Confederation Line Project, AW Hooker, is actively reviewing project progress and certifying payments as part of their services to the Project. The IC’s role is bound by the Project Agreement and the City can rely on their services for completion of the contractual requirements.
In addition to the Project Agreement requirements outlined above, a variety of independent regulatory bodies, including the City’s Building Code Services, the Technical Standards & Safety Authority (TSSA), and Ottawa Fire Services play an important role in ensuring that station and systems elements meet pertinent code requirements.
Overall Stage 1 – Stage 2 Extension Integration
The works and oversight described are in relation to the infrastructure being delivered by EWC only. In order to provide a complete view of the expanded Confederation Line, it is important to outline the various inputs that are required for vehicles, systems, infrastructure, operations and maintenance and how they are verified and validated as a complete unit.
SENER, as Independent Safety Auditor, will provide a safety audit of the complete, expanded system on behalf of the City to ensure that the integrated solution meets the safety requirements.
Moreover, the coordination and integration of various scopes of work will be demonstrated as an integrated system through the Trial Running period. The Trial Running period, in the context of a system extension, is an EWC contractual requirement to test and exercise the respective System Infrastructure, including all subsystems, that comprise the relevant works, operating personnel and operating procedures to demonstrate the East Works and West Works can reliably implement passenger service without interruptions. Further details on the Trial Running process for the Confederation Line will be provided in 2024 and the full definition of Trial Running is provided in Schedule 14 listed on the City of Ottawa’s Routine Disclosure webpage.
Should you have any questions about the information provided in this memo, please do not hesitate to contact me at extension 52718.
Original signed by
Michael Morgan
Cc: Senior Leadership Team
Transportation Services Departmental Leadership Team
Director, Public Information and Media Relations
To: Mayor and Members of Council
From: Renée Amilcar, General Manager, Transit Services Department
The purpose of this memo is to advise the Mayor and Members of Council that, as part of OC Transpo’s Bus Route Review discussed at Transit Commission, consultations with Council and the public process will begin shortly.
With changes to ridership since the onset of the COVID-19 pandemic, and with the upcoming opening of the Stage 2 O-Train extensions, there is a need to optimize our existing transit system.
This review aligns with the ongoing City service reviews being coordinated by the Service Review Working Group. Upon the conclusion of this process, OC Transpo will be able to optimize routes to support residents’ changing transit needs, while also responding to new realities, such as hybrid work, and to make policy recommendations to Council, if required.
As part of the review, transit customers, Councillors, customer advocacy groups, major employers, OC Transpo employees and other stakeholders will be engaged in a variety of different consultations:
Transit Services will be providing Councillors with information packages to facilitate outreach in their wards.
To support the work required to complete this review, the core project team has engaged Dillon Consulting. Dillon was prequalified for this type of work through the City’s standing offer list. They will be working closely with our subject matter experts and bring expertise in planning, engineering, environmental science, and management.
If you have any questions or comments, contact Scott Laberge, Associate Director Transit Customer Systems and Planning, at extension 14120.
Original signed by, Renée Amilcar
c.c.: Senior Leadership Team Transit Services Departmental Leadership Team Director, Public Information and Media Relations
To: Mayor and Members of Council
Chair and Members of the Transit Commission
From: General Manager, Transit Services Department
The purpose of this memo is to advise the Mayor and Members of Council that O-Train Line 1 service will be adjusted on Saturday, April 29 and Sunday, April 30, and on Saturday, May 6 and Sunday, May 7 for the partial closure of the downtown tunnel, due to a necessary maintenance assessment.
This work must occur for Rideau Transit Group (RTG) to assess the scope of required repairs to prevent water infiltration in sections of the tunnel. This type of regular maintenance is common for underground tunnels, and there are no safety concerns.
This RTG assessment is necessary and will provide the basis for the development of a workplan for scheduled tunnel maintenance work in June. Information about this June maintenance work will be communicated to Council in advance.
Information and reminders will be communicated to customers in advance of the April and May planned maintenance through various channels, including a Public Service Announcement, customer alerts, social media updates, signage at Line 1 stations, and on octranspo.com.
Customers can visit octranspo.com for travel planning assistance or call 613-560-5000. OC Transpo Red Vest staff will be present across the system and stationed at key areas to assist customers throughout the duration of the temporary service adjustments.
Staff will be pleased to answer questions about the upcoming temporary closures in April and May at tomorrow’s Transit Commission meeting and can answer media questions during the media availability immediately following.
If you have any questions, please contact Troy Charter, Director, Transit Service Delivery and Rail Operations, at ext. 52160 or me at ext. 52111.
Original signed by
Renée Amilcar
cc: Senior Leadership Team
Transit Services Departmental Leadership Team
Director, Public Information and Media Relations
To: Mayor and Members of Council
Chair and Members of the Transit Commission
From: General Manager, Transit Services Department
The purpose of this memo is to provide the Mayor and Members of Council with an overview of OC Transpo’s spring service changes, effective Sunday, April 23, 2023. Regular schedule adjustments take place four times a year – spring, summer, fall and winter – and memos are provided in advance of each new schedule period.
The spring service change includes several types of changes:
Service Adjustments
Service Adjustments for Construction
Seasonal Service Changes
Holidays
Day | Date | Bus Service Level | O-Train Line 1 Service Level | Line 2 Bus Service Level |
Victoria Day | Monday, May 22 | Sunday schedule | Sunday schedule Hours: 8 am - 11 pm |
Sunday schedule Hours: 7:15 am – 11 pm |
Canada Day | Saturday, July 1 | Special Canada Day schedule | Special Canada Day schedule Hours: 6 am - 2 am |
Special Canada Day schedule Hours: 7:15 am – 1 am |
Customer information
Full details of these service changes will be communicated to customers throughout April. OC Transpo has several customer-friendly applications and tools to assist customers in accessing timely information about our service while on the go. These include texting 560560 for real-time bus schedule information, downloading an independent app, signing up for text alerts to receive the latest information, checking transit information screens at many major stations, as well as visiting octranspo.com from a smartphone. Real-time information is also available by calling 613-560-1000 plus the bus stop number.
Once the spring service changes begin on April 23, customers can find up-to-date schedules and real-time information by using these applications and tools. Please direct customers to octranspo.com or to the OC Transpo Customer Service Centre (613-560-5000) for more information.
These spring service changes will be evaluated based on feedback we collect from customers and operating staff, as well as ridership and operational data measurements. Our goal is to continue to provide excellent service for customers as their travel needs change.
Should you have any questions or comments, please contact Scott Laberge, Associate Director, Transit Customer Systems and Planning, at extension 14120.
Original signed by
Renée Amilcar
cc: Senior Leadership Team
Transit Services Departmental Leadership Team
Director, Public Information and Media Relations
Following the discussions on the 2023 draft budget at Transit Commission on February 9, some Members of Council have asked for more clarity regarding the draft budget and what it means for OC Transpo’s customers. The purpose of this memo is to provide Members of Council with further information regarding OC Transpo’s proposed 2023 budget.
OC Transpo is committed to delivering the best possible service for our customers and in this draft budget we are not proposing any overall service cuts. The budget process provides an opportunity to recalibrate our investments in our transit system and ensure we continue to meet the evolving needs of our customers. In the draft budget, OC Transpo is making needed investments to meet the new post-pandemic travel needs of our customers.
OC Transpo has both operating and capital budgets.
The proposed operating budget for will be $17 million higher and includes significant service increases that will have a positive impact for customers. Operating budgets fund ongoing expenses such as staff salaries and diesel fuel costs
The proposed capital budget for OC Transpo calls for new investments of $122 million, to add to the continued delivery of $782 million in previously approved capital projects. Capital budgets are used to make long-term investments in infrastructure and other assets.
For customers, this means that they will continue to see improvements across the transit system due to investments within both the capital and operating budgets. At a high level this includes:
Enhancements |
Investment |
System Improvements |
Opening the expanded O-Train Line 2 (Bayview to Riverside South) and the new O-Train Line 4 to the airport |
$16 million |
12-minute service, seven days a week, between 13 stations (8 new), using 13 trains (7 new), over the north-south corridor. |
Electrification of bus fleet |
$335 million in City funding, combined with $639 million in federal loans and grants |
All new OC Transpo conventional buses will be powered by electricity, resulting in reduced emissions and a quieter, smoother ride. |
New operators |
Hiring 360 rail and bus operators in 2023 |
Many newly hired operators will replace others who are retiring. Others will support the opening of the two new O-Train lines, and others will increase the workforce to improve the reliability of all parts of the transit system. |
Fare freeze |
$5 million |
Council is investing $5 million in keeping fares unchanged from 2022, to make it easier for everyone to choose transit for their travel |
Renewal of city assets |
$97 million |
This includes things like bus replacement Para Transpo minibuses, infrastructure rehabilitation, and work to be ready for the opening of the Stage 2 O-Train extensions. |
Technology and accessibility |
$25 million |
Technology investments will improve information for customers and will sustain a reliable transit service. Accessibility investments will remove barriers to travel for people with disabilities. |
While making these investments in our service, the draft budget also takes a prudent approach to managing taxpayers’ money. For example, The City enters into hedging contracts for diesel fuel to provide greater budget certainty and guard against potential price fluctuations. The city fixes prices for 75% of the expected volume over the next eight months and hedges to lesser amounts further out on a rolling basis. Additionally, like many other transit agencies around the world, we are seeing increases in costs in many areas due to inflation. For items like fuel, wages and contracts the cost of inflation is about $28.1 million. Wages and contracts are increasing at the same pace as previous years, but the price of fuel is estimated to increase by 37% over 2022 budgeted prices. The construction price index has increased to 6.3%, resulting in $6.2 million in added costs that must be accommodated in the capital budget.
While there have been good increases in ridership in recent months, there are still about 30% of customers who are not expected to return in 2023, compared to 2019 levels, largely because many office workers are continuing to work full-time or part-time from home. This amounts to approximately a $53 million fare revenue shortfall. In January 2023, ridership was 62% compared to 2019 levels, which is aligned with staff projections. This increase is based on the start of the gradual return to on-site work by employees of the federal government, the largest employer in Ottawa.
To respond to the new and increasing costs and the fact that ridership and fare revenue remain below pre-pandemic levels, OC Transpo is proposing a number of savings for 2023 that better align our costs with service levels that follow the needs of our customers. For example, prior to the pandemic OC Transpo required 851 conventional buses to deliver service. When ridership levels fell due to the pandemic, these buses were retained in the fleet because it was unknown how quickly the City economy and transit ridership levels would recover. Now that ridership patterns are more stable, this budget is proposing a realignment of OC Transpo’s bus fleet size to 738 to match actual service needs. For OC Transpo this means avoiding $4.4 million in maintenance costs and $3.7 million in capital costs in 2023 by retiring older vehicles. For customers this means the same number of buses on the road and the same schedules they are familiar with. No changes to service will be made because of this fleet realignment, and we will continue to have enough buses to meet the demands of our growing city for this year and next.
This and other prudent savings proposed in the draft budget allow us to provide a more reliable service and to continue to invest in customer improvements.
In addition, due to the ongoing impacts of COVID-19, we have notified the province of needing $53 million under the Safe Restart Agreement program to cover the shortfall in fare revenue. The City will need to receive at least $39 million to balance the budget. This request is lower than previous years as we continue to lower our dependency on senior levels of government, while considering service delivery needs and financial risks. Should the Provincial contributions fall below the minimum requirements, we have alternative options ready, including drawing from reserves to make up the shortfall or bringing options for further cost savings to the Transit Commission for consideration.
Following the adoption of the 2023 budget, OC Transpo will also be undertaking a review of all bus routes. As ridership patterns have changed due to the pandemic, we must adapt the system to this new reality to continue to deliver the best possible service to our customers. This will involve evaluating potential future networks and identifying potential changes to service policy. Throughout this process consultations with customers and stakeholders will occur. Recommendations will be brought to Transit Commission later this year.
As described above, OC Transpo continues to make investments to improve the customer experience and improve the service we deliver to them.
Original signed by
Renée Amilcar
cc: Senior Leadership Team
Transit Services Departmental Leadership Team
Director, Public Information and Media Relations
To: Mayor and Members of Council
From: Renée Amilcar, General Manager, Transit Services Department
The purpose of this memo is to inform Members of Council that the Transportation Safety Board of Canada (TSB) issued a Rail Safety Advisory (RSA) letterOpens in a new tab or window(link is external) on February 3, 2023, regarding O-Train Line 1 vehicle axle bearing assemblies. This work is the result of its investigation that commenced after the August 2021 derailment and the July 2022 wheel axle hub event. OC Transpo and Rideau Transit Group (RTG) have reviewed the letter, met with TSB, and staff are now in a position to provide this letter to Council.
The City of Ottawa has an agreement with TSB, setting out the process for both parties to conduct their own investigations on O-Train Line 1. The City benefits from having TSB as external investigators for accidents and events, as it is an expert in post-incident investigations. TSB input has significantly contributed to enhancing the robust safety measures of our light rail system. Staff thank TSB for its timely investigations and communications, and City staff have fully cooperated with its work.
After reviewing the letter, OC Transpo and RTG can confirm that all enhanced system safety measures in place align with TSB suggestions. RTG has provided the City with written confirmation that the O-Train Line 1 system is safe. Staff are currently reviewing TSB’s findings in detail; this information will assist RTG in completing the final root cause analysis into the wheel axle hub assembly issue.
The safety of Transit customers is paramount. As discussed at Council in July 2022, out of an abundance of caution, while the root cause investigation of the axle bearing assembly is underway, enhanced mitigation measures are in place to ensure that the trains and system are safe:
In accordance with standard operating procedures, Rideau Transit Maintenance (RTM) inspects all light rail vehicles daily, prior to every launch
All leading and trailing bogie axles are replaced when they reach 175,000 km of service and are inspected for bearing assembly free play every 7,500 km
The remaining axles are inspected at every 3,750 km when they exceed 175,000 km
Temporary Speed Restrictions are in place at several locations along the alignment
OC Transpo hosts weekly status meetings on the root cause analysis with RTG, RTM, OLRT-C and its subcontractors
RTG has installed vibration monitoring equipment on some trains and plans to expand the installation on additional vehicles in the coming months.
The final root cause analysis is ongoing, and the recent settlement agreement with RTG implements a solid plan that actions the TSB recommendations to resolve these issues. Staff will present the findings and recommendations to Council for consideration once this is complete. The City continues to work collaboratively with RTG and is actively monitoring its work and progress. Our shared goal is to determine the final root cause of this issue and implement a solution that makes O-Train Line 1 operations sustainable and reliable.
Original signed by
Renée Amilcar
cc: Senior Leadership Team
Transit Services Departmental Leadership Team
Director, Public Information and Media Relations
To: Mayor and Members of Council
From: Cyril Rogers, Acting Chief Financial Officer/Treasurer and Troy Charter, Acting General Manager of Transit Services
The purpose of this memo is to advise Mayor and Members of Council that a report providing a financial update on the Zero-Emission Bus (ZEB) Program will be part of the Council agenda posted on ottawa.ca on Friday, January 20, for Council consideration at its meeting on Wednesday, January 25.
The report provides an update on Canada Infrastructure Bank and Infrastructure Canada funding for the ZEB program. We are pleased to advise that we have successfully concluded funding from both agencies and are seeking approval of budget authority for the program to begin the procurement of OC Transpo zero-emission buses and related charging infrastructure.
You are invited to attend an announcement by the Government of Canada on Thursday, January 19 at 9 am at OC Transpo, 1500 St. Laurent Boulevard. Please RSVP by emailing Kavita.Gaur@ottawa.ca.
The Zero-Emissions Buses for OC Transpo report was approved by Council on June 23, 2021. Pending funding availability, the program could allow OC Transpo to achieve a fully zero-emission bus fleet by 2036.
Converting OC Transpo’s bus fleet from diesel-powered vehicles to electric is a key component of the City of Ottawa’s Climate Change Master Plan, the City’s overarching framework to reduce greenhouse gas emissions and respond to the current and future effects of climate change.
Should you have any questions or comments, please contact Isabelle Jasmin, Deputy City Treasurer, Corporate Finance, at extension 21312.
Original signed by
Cyril Rogers & Troy Charter
cc: Senior Leadership Team
Transit Services Departmental Leadership Team
Director, Public Information and Media Relations
OC Transpo reports to the Transit Commission monthly and the Light Rail Sub-Committee when meetings are called. Links to each meeting’s agenda and live-captured video are available.
April 13, 2023
March 3, 2023
February 9, 2023
January 27, 2023
May 26, 2023
April 28, 2023
March 29, 2023
February 16, 2023
The City of Ottawa presented its action plan in response to the Ottawa Light Rail Transit Public the Light Rail Sub-Committee on April 28. The final report from the inquiry, which was published in December 2022, includes 103 recommendations. Currently, 36 of the 103 recommendations are complete or have been incorporated into ongoing City policies for implementation into future projects. The remainder of the recommendations are in progress and expected to be completed by the end of 2023. The action plan will be updated regularly on this page to allow the public to stay up to date on the City’s progress.
OC Transpo is committed to improving the reliability and maintaining the safety of O-Train Line 1, as well as preparing for future light rail transit expansions and other major infrastructure projects by incorporating lessons learned from Stage 1 and the recommendations of the public inquiry.
The Dashboard tab provides a brief summary of items completed, in progress, or for the Provincial Government's consideration. The Action plan items tab includes updated tables of the 103 recommendations and their statuses.
Theme | Number of items that are complete | Number of items that are in progress | Number of items that are for the Provincial Government’s consideration |
---|---|---|---|
Planning Complex Infrastructure
|
6
|
1
|
|
Preparing Projects Estimates and Budgets
|
2
|
3
|
|
Selecting a Project Delivery Model
|
4
|
||
Risk Reduction during Procurement
|
2
|
2
|
|
Creating an Effective Contract Scheme
|
8
|
15
|
1
|
Fostering Successful Working Relationships
|
2
|
1
|
|
Transparency and Effective Planning and Oversight during Construction
|
12
|
||
Accuracy, Transparency, and Public Entity Decision-Making
|
3
|
1
|
|
Safety Requirements
|
2
|
1
|
|
Preparing for and Achieving a Successful Handover & Start to Public Service
|
1
|
8
|
|
Public Service
|
4
|
7
|
1
|
Recommendations for the OLRT1
|
4
|
12
|
|
Totals
|
36
|
59
|
8
|
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
1 |
Public entities, and their representatives, should take care to ensure that the priorities they set for complex infrastructure projects are appropriately applied throughout the planning and implementation stages of the project. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4, 2023. Any policy or procedure changes will be communicated to City staff. The P3 model is not commonly used by the City of Ottawa for complex infrastructure projects. However, Supply Services will update the P3 Policy to highlight the need for Departments to ensure priorities are appropriately aligned throughout the planning and implementation phases of a project. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4, 2023. Supply Services will update the P3 Policy by the end of Q3 2023. |
2 |
Public entities should consider ways they can identify and address the root causes of cognitive biases. Optimism bias in project planning, for example, leads people to underestimate project costs and risks. Public entities should consider using established approaches such as reference class forecasting, which uses data about prior projects and their outcomes to account for unconscious biases and unanticipated risks. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4 2023. Any policy or procedure changes will be communicated to City staff. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. Infrastructure and Water Services agrees and will support actioning the recommendation. |
3 |
Public entities should also strive to avoid “uniqueness bias” – the belief that the project being planned is unique and not comparable to others. Instead, public entities should identify similarities to established projects and learn from the outcomes of those projects. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4, 2023. Any policy or procedure changes will be communicated to City staff. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4, 2023. Infrastructure and Water Services agrees and will support actioning the recommendation. |
4 |
Public entities should avoid, wherever possible, introducing complexity into the major components of the project. For example, if there are to be several stations on a rail line or similar project, keep the differences between the stations to a minimum. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4, 2023. Any policy or procedure changes will be communicated to City staff. Supply Services will update the P3 Policy to highlight the need for Departments ensure complexity is avoided whenever possible. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4, 2023. Supply Services will update the P3 Policy by the end of Q3 2023. Infrastructure and Water Services agrees and will support actioning the recommendation. |
5 |
Public entities should ensure, from the project outset, that they have access to the expertise that will be required throughout the project, in order to effectively engage in and oversee the project’s development from planning through to public launch. |
Finance and Corporate Services |
The City’s P3 Policy currently addresses this requirement. The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4, 2023. Any policy or procedure changes will be communicated to City staff. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4, 2023. |
6 |
A detailed Concept of Operations should be prepared before the preliminary design of the project, and where the operation of the system is not being contracted out, ideally before the project agreement is finalized. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4, 2023. Any policy or procedure changes will be communicated to City staff. The concept was introduced partway through Stage 1, and the work is included in the Stage 2 and Stage 3 programs. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4, 2023. Transit Services has incorporated a Concept of Operations into the Stage 2 and Stage 3 programs. |
7 |
The Province of Ontario should investigate how to develop the skills and capabilities at the municipal level required to lead large infrastructure projects. For example, the province may wish to consider: a. Creating a training program like the Major Projects Leadership Academy at Oxford University in England, to instill and improve the project management skills required for complex infrastructure projects at the municipal level; b. Creating career paths within government to encourage civil servants to develop and use the project management skills and experience they gained through training or on previous complex infrastructure projects; and c. Ensuring that municipalities undertaking complex infrastructure projects have ongoing access to expert advice and guidance throughout the project, from procurement through to construction and operations, particularly with respect to managing the relationship with the private-sector partner. |
Government of Ontario |
N/A |
For the Provincial Government’s consideration |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
8 |
Public entities should clearly communicate (to elected officials, the public, and other stakeholders, as appropriate) any restrictions, caveats, or limitations applicable to cost estimates developed during the planning of complex infrastructure projects. They should also clearly communicate that such estimates are subject to change as the project planning progresses. Particularly when communicating with the public, public entity representatives should not commit to an estimate as if it were a set budget for a project. The public should be accurately informed about the status of the estimate and, where the estimate is subject to change, that fact should be clearly communicated. |
Office of the City Clerk Transit Services Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4 2023. Any policy or procedure changes will be communicated to City staff. The Project Delivery Review and Cost Estimating report (ACS2013-PAI-INF-0012) was approved by Council in 2013. This report provides a cost estimate classification system and a reporting mechanism to Council where cost estimates for capital projects are provided and future capital budget documents to ensure consistent methods of estimating to total project costs. Legal Services is undertaking a review of the Employee Code of Conduct, with updates anticipated for Q1 of 2024. The revised Code will reinforce staff’s obligations with respect to transparency and accountability. Supply Services will update the P3 Policy to highlight the need for Departments to effectively communicate any restrictions, caveats, or limitations applicable to cost estimates when seeking Council authorization. Transit Services management will work with other levels of government to assess funding agreements for increased flexibility with funding levels as project needs evolve, increased flexibility of eligibility criteria for costs, increased flexibility in timing for determination of final contribution amounts, and more generally, increased flexibility in administration of transfer payment agreements. The Project Delivery Review and Cost Estimating report (ACS2013-PAI-INF-0012) was approved by Council in 2013. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. Supply Services will update the P3 Policy by the end of Q3 2023. |
9 |
Public entities should avoid setting budgets too early, and remain flexible as project cost estimates evolve during the planning for such projects. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4, 2023. Any policy or procedure changes will be communicated to City staff. The Project Delivery Review and Cost Estimating report (ACS2013-PAI-INF-0012) was approved by Council in 2013. This report provides a cost estimate classification system and a reporting mechanism to Council where cost estimates for capital projects are provided and future capital budget documents to ensure consistent methods of estimating to total project costs. Transit Services management will work with other levels of government to assess funding agreements for increased flexibility with funding levels as project needs evolve, increased flexibility of eligibility criteria for costs, increased flexibility in timing for determination of final contribution amounts, and more generally, increased flexibility in administration of transfer payment agreements. |
In Progress Investigating which City policies can be updated to incorporate this recommendation as a best practice. Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. |
10 |
The Province of Ontario and the federal government should review the process for determining the size of funding contributions to municipal infrastructure projects and, where required, make changes to that process to ensure that such funding contributions are not based on preliminary estimates that do not end up accurately reflecting the true costs of the project. |
Government of Ontario Government of Canada |
N/A |
For the Provincial and Federal government’s consideration |
11 |
Where the Province of Ontario and/or the federal government are contributing to the funding of a project, they should incorporate some flexibility to respond to the evolving project needs. |
Government of Ontario Government of Canada |
N/A |
For the Provincial and Federal government’s consideration |
12 |
Where a senior level of government requires that a particular project delivery model, such as a public-private partnership (P3), be used by a municipality as a condition of senior government funding, that government should ensure that the costs associated with that model are eligible for coverage by the senior government funding. For example, where a P3 model is to be used, the financing costs of the P3 should qualify as eligible expenses. |
Government of Ontario Government of Canada |
N/A |
For the Provincial and Federal government’s consideration |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
13 |
When selecting a delivery model for a complex infrastructure project, the public entity should use objective criteria appropriate to the project’s circumstances to evaluate the available delivery models, including: a. The model’s comparative value from the perspective of quality, cost, and schedule as compared with other approaches; b. Whether the model properly aligns the interests of the parties involved, and whether the project risks will be managed by the parties best positioned to handle them. Consideration should be given to whether the transfer of specific risks, in whole or in part, is likely to encourage or undermine collaborative behaviour between the parties working on the project; c. The incentives and tools that each model offers to enforce contractual obligations; d. The measures each model has in place to ensure public transparency, accountability, and oversight of major infrastructure projects; e. The degree of control the government authority should retain, given the project’s circumstances and the public authority’s experience; f. The degree of flexibility each model offers to the public entity to alter the infrastructure over the project’s life without facing major contract change fees; and g. The manner and extent to which each model prioritizes the public interest. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4, 2023. Any policy or procedure changes will be communicated to City staff. Supply Services will update the strategic assessment criteria outlined in the P3 Procedures used by Departments to assess project delivery models. Transit Services management acknowledge and agree with this recommendation related to the delivery model of a complex infrastructure project. The recommendations that have comparative value, level of project controls, evaluation criteria, and the benefits and drawbacks should be clearly articulated as part of selecting a delivery model. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. Supply Services will update the P3 Policy by the end of Q3 2023. |
14 |
The public entity should ensure that the evaluation criteria used accurately reflect all the priorities set for the project. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4, 2023. Any policy or procedure changes will be communicated to City staff. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. |
15 |
The public entity should ensure that the potential benefits and drawbacks associated with each delivery model are identified and considered. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4 2023. Any policy or procedure changes will be communicated to City staff. Transit Services management acknowledge and agree with this recommendation related to the delivery model of a complex infrastructure project. The recommendations that have comparative value, level of project controls, evaluation criteria, and the benefits and drawbacks should be clearly articulated as part of selecting a delivery model. The City’s P3 Policy and Procedures currently requires that a strategic assessment of the benefits and risks of delivery models be identified and considered. Supply Services will update the P3 Policy to highlight the need for Departments to effectively communicate the benefits and drawbacks of various delivery models when seeking Council authorization of the recommended approach. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. Supply Services will update the P3 Policy by the end of Q3 2023. |
16 |
In considering a delivery model that requires the private sector to provide project financing, care must be taken to ensure that the rights accorded to private creditors do not create additional risks for the project. For example, where changes to the project require creditor consent, limits should be placed on the additional equity they can demand as a condition to their consent. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4, 2023. Any policy or procedure changes will be communicated to City staff. Transit Services management acknowledge and agree with this recommendation related to the delivery model. The recommendations that have comparative value, level of project controls, evaluation criteria, and the benefits and drawbacks should be clearly articulated as part of selecting a delivery model. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
17 |
Introducing new or untested project elements (including technology and workforce) increases project risk. Where possible, public entities should give preference to using service-proven designs, components, labour markets, and supply chains. This is particularly so for key project components, components that present the most inherent risk, and components that cannot be quickly and cost-efficiently replaced in the event of a problem. For example, LRVs should be built in dedicated manufacturing facilities, and ideally in a pre-existing LRV production facility. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4 2023. Any policy or procedure changes will be communicated to City staff. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. |
18 |
Regarding the Province of Ontario’s Canadian Content for Transit Vehicle Procurement Policy established in 2008, the province should study how to strike the right balance for the policy, so the goals of industrial and skills development can be addressed without requiring a single project to take on the costs and risks of creating new skilled manufacturing jobs. For instance, a price preference could be applied, or another advantage given, depending on the Canadian content a bidder includes in its bid. Any waivers or accommodations should be broad enough to account for the current limitations of the Canadian market and ensure transit operators are able to obtain a quality product produced by a qualified workforce and for the public interests. |
Government of Ontario |
Transit Services will consult with the Province of Ontario regarding this requirement for future procurements of transit vehicles. |
For the Provincial Government’s consideration |
19 |
The Province of Ontario should consider requiring that key project components be service proven. If this requirement is implemented, any applicable local content requirements should include waivers, exemptions, or other means to allow for such service-proven components to be used. |
Government of Ontario |
City management acknowledges this recommendation and will consult with the Province of Ontario regarding this requirement for future procurements. |
For the Provincial Government’s consideration |
20 |
A public entity may include elements in its procurement process that could result in the introduction of new components to respondents’ bids during the in-market period. For example, if the public entity includes a pre-qualification process for suppliers during the in-market period, a bidder whose proposed supplier is disqualified during that process must source and incorporate a different supplier into its bid. When the procurement process includes steps that may result in the introduction of new components to respondents’ bids during the in-market period, the public entity should ensure that respondents are given adequate time to incorporate those new components into their bids. This should be accounted for in the procurement plans. |
Supply Services |
Supply will update the Procurement Manual to add clarity around timelines for amendments during the in-market period. City management acknowledge and agree with this recommendation. Recent procurements for Stage 2 and the Confederation Line project included pre-qualifying suppliers as part of its process to allow for bidders to meet with qualified suppliers prior to their bid submission. |
In Progress Supply can commit to updating the Procurement Manual by the end of Q2 2023. |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
21 |
The public-sector entity should consider retaining (or empowering) an independent advisor with expertise in the type of project to be constructed to ensure that any draft project agreement used as a starting point for negotiations reflects best practices and does not include scope gaps. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4 2023. Any policy or procedure changes will be communicated to City staff. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. |
22 |
The project agreement should address responsibility for public communications to ensure timely and accurate information is provided during the life of the project. |
Supply Services Transit Services |
Supply Services will update the P3 Policy to specifically identify responsibility and requirements for project communications as an element to be included in the Project Agreement. |
In Progress Supply Services will update the P3 Policy by the end of Q3 2023 |
23 |
The project agreement should provide for meaningful involvement from the public-sector and private-sector parties in all public communications about the project. |
Supply Services Transit Services |
Supply Services will update the P3 Policy to specifically identify responsibility and requirements for project communications as an element to be included in the Project Agreement. |
In Progress Supply Services will update the P3 Policy by the end of Q3 2023 |
24 |
The project agreement should require that communications to the public be accurate and well founded. Uncertainty should be acknowledged. |
Supply Services Transit Services |
Supply Services will update the P3 Policy to specifically identify responsibility and requirements for project communications as an element to be included in the Project Agreement. |
In Progress Supply Services will update the P3 Policy by the end of Q3 2023 |
25 |
The project agreement should require that communications to the public be focused at all times on furthering the public interest. |
Supply Services Transit Services |
Supply Services will update the P3 Policy to specifically identify responsibility and requirements for project communications as an element to be included in the Project Agreement. The Stage 2 Project Agreement includes a robust communications strategy designed to ensure transparency with Council, public, media and stakeholders. Transparency on the project schedule, including any issues or delays, is key to retaining the public’s trust. Transit Services will continue with ongoing Stage 2 community and stakeholder outreach. Staff will continue to provide communication to Council through bi-weekly construction updates, quarterly construction memos and presentations to the Light Rail Sub-Committee. Building upon the work already in progress, Transit Services is creating an information campaign to educate and build excitement for the O-Train expansion. This includes web, social, events, and outreach, which will be incorporated into a larger strategy to improve customer communications and build public trust. |
In Progress Supply Services will update the P3 Policy by the end of Q3 2023 |
26 |
Within a given model, the early resolution of disputes should be incentivized in the project agreement, particularly where those disputes will affect the work going forward. Resolving operational problems and providing reliable public service must take precedence over all other priorities, including contract enforcement. The resources necessary to address a problem should be mobilized ahead of contractual interpretation and dispute resolution. This could all be done without prejudice to the parties’ claims against one another. |
Supply Services |
While this is currently a requirement of the Contract Administration Policy, Supply Services will update the Policy to clarify that the overarching objective of timely dispute resolution is to ensure the continuation of reliable public service. |
In Progress Supply Services will update the P3 Policy by the end of Q3 2023 |
27 |
The provincial government should investigate how to better incentivize in P3 contracts the timely solution of infrastructure problems to avoid delay due to disputes between the parties. Positive and negative incentives should be considered. For example, positive incentives might include a break in payment mechanism deductions if significant problems are resolved before a Key Performance Indicator (KPI) deadline in the contract. |
Government of Ontario |
N/A |
For the Provincial Government’s consideration |
28 |
Project partners must clearly define the roles of the safety auditor and the Independent Certifier, and agree upon the nature and degree of assurance each can provide. |
Transit Services |
Transit Services agrees with the recommendation and considers it complete. As noted in memos sent to Council in August 2022 and April 2023, an independent System Integration Verifier and Independent Certifier have been identified and contracted to oversee the Stage 2 project extensions. |
Complete |
29 |
Where amendments to contracts are being considered, relevant and affected parties should be involved in those discussions, including relevant subcontractors. |
Transit Services |
Transit Services agrees with the approach and it is standard practice to ensure that affected parties are included in the development and agreement to contracts. The current practice with contract variations is to ensure that both the constructor and the maintainer provide input to the contract changes. For the Confederation Line extension project, a formalized process for the maintainer to identify “divergences” or cost impacts has been established to ensure that there is a process for dealing with changes that will affect their work. |
Complete |
30 |
Construction contracts should include mechanisms for calculating extensions of time and adjusting schedules if obstacles arise and delays are encountered. |
Transit Services |
Project Agreements include standard provisions for dealing with different types of time extensions and for handling impacts if there are obstacles that are encountered. |
Complete |
31 |
Specific testing and commissioning requirements should be clearly defined in the project agreement. In the case of large or complex LRT projects, these should account for a sufficient period of integration testing. In the case of an LRT system, the train manufacturer should also be involved. |
Transit Services |
The approach to integration testing has changed in Stage 2 to require the application of European (EN) standards, amongst others, to ensure that a rigorous process is in place to deal with systems integration and integration testing more broadly. Furthermore, a new Systems Integration Verifier role has been added to Stage 2 that will work to ensure the integration of the headend equipment at the Transit Operations Control Centre and the field equipment is properly completed. This role is intended to review integration issues between the City’s delivery scope in the control centre and Project Co’s delivery scope in the field; the role does not consider other integration that is otherwise covered by the project delivery teams. In instances where the integration work is fully within Project Co’s remit, systems integration will be led by the Project Co’s Systems Integration Manager. Finally, the vehicle manufacturer is included in the overall test programme for their elements of the work. |
Complete |
32 |
In locations with unusual climatic conditions, or climates that vary dramatically, a provision should be made for climate-specific testing of the full system, including dynamic testing. For instance, there should be specific requirements for dynamic winter testing – not merely testing during the winter – in locations like Ottawa that have a severe winter climate. |
Transit Services |
For the Trillium Line, the existing Alstom LINT vehicles have been tested in service during multiple Ottawa winters. The new Stadler FLIRT vehicles have been tested in winter periods and will be used for the first time in passenger service during the 2023-2024 winter period. Backup bus service will remain in place throughout the first winter of service. For the Confederation Line, multiple changes have been made to the vehicles and infrastructure to improve winter performance. In the run-up to service on the east, the infrastructure and vehicle will be tested over the 2024-2025 winter period. |
Complete for Stage 1 In Progress for Stage 2 |
33 |
Trial running standards should be set out in detail in the relevant contracts. Minimum standards should be set at the outset of the project for both duration and scoring. The scoring should be based on the same performance specifications that the parties have agreed to apply to the system in operation. |
Transit Services |
The City has added specific criteria into the Stage 2 agreements in order to address this gap. The additional criteria for Trial Running have been included in the contract and are based on the performance specifications that the parties have agreed to apply to the system in operation. |
Complete |
34 |
As with testing, the circumstances imposed during the trial running period must mirror as closely as possible the actual public operation of the service. For example, the trial running for transit must mirror intended ridership, climatic conditions, and realistic rider use (e.g., holding, blocking, and pushing the doors). The trial running criteria must be established with a view to having the system consistently demonstrate that it can achieve those criteria based on anticipated ridership and service conditions. |
Transit Services |
The City has added specific criteria into the Stage 2 agreements in order to address this gap. The additional criteria for Trial Running have been included in the contract and are based on the performance specifications that the parties have agreed to apply to the system in operation. Additionally, the requirements and criteria need to be achieved over a longer period to demonstrate consistency. |
Complete |
35 |
An independent expert should be appointed, either individually or as part of a panel with representatives from key stakeholder groups, who must (i) assess trial running criteria and performance, and (ii) approve any material change to the trial running criteria or process. |
Transit Services |
An independent third-party is in the process of being appointed to take on this function and will be in place to provide oversight for Trial Running. |
In Progress |
36 |
There must be proper documentation of any material changes to the trial running criteria with an explanation, analysis, and approval of such changes to be clearly recorded in writing. |
Transit Services |
An independent third-party is in the process of being appointed to take on this function and will be in place to provide oversight for Trial Running. Material changes are unlikely but if required, would be documented by the City and presented to Council in order to provide full transparency and documentation of the change. |
In Progress |
37 |
Maintenance work and systems should be meaningfully and objectively evaluated during trial running, and any failures that would impair public use of the asset if they occurred during public operation should be treated seriously in the evaluation process. |
Transit Services |
Evaluation of maintenance practices will be evaluated during Trial Running process and will be reported out as part of final demonstration that the system is ready for service. |
Complete |
38 |
The relevant project contracts should account for a bedding-in period prior to public service (revenue service) – a period of extensive running of the fully integrated system in real operating conditions prior to public launch. Such a bedding-in period gives operations and maintenance staff real-time experience of the system before the public is asked to rely on it. The length of the bedding-in period should: a. Be appropriate to the project (including its technical complexity and inherent risk profile); b. Account for any aspects of the project that increase the risk of hidden issues arising; and c. Include a series of predetermined troubleshooting scenarios that mimic the kinds of incidents that could arise during public service. This will allow all involved in the operation and maintenance of the infrastructure to learn and foster a collaborative relationship between those who will be directly involved once the asset begins serving the public. |
Transit Services Supply Services |
Transit Services will assess the opportunity for a period of extensive running of the fully integrated system prior to launch. The running of the complete system and the application of a longer Trial Running period will be used to develop the level of proficiency of the operations teams and the maintenance teams prior to service. Equally, the Trial Running period will include a series of troubleshooting shooting to ensure that the teams are properly trained to deal with issues that arise in service. Supply Services will update the P3 Procedures to include a bedding-in period as a consideration. |
In Progress Supply Services will update the P3 Policy by the end of Q3 2023 |
39 |
Greater consideration should be given to a gradual or soft start to public service (revenue service), particularly when all systems and infrastructure on a project are new. This should be accounted for in the relevant project contracts. |
Transit Services Supply Services |
Transit Services will assess the opportunity for a period of extensive running of the fully integrated system prior to launch. For Stage 2 of the Trillium Line, the decision has been taken to retain the replacement buses in service over the first winter period in order to help reduce the pressure on the new service and to ensure that alternative service is readily available if there is an issue with rail service. Supply Services will update the P3 Procedures to include a soft-start to public service as a consideration. |
In Progress Supply Services will update the P3 Policy by the end of Q3 2023 |
40 |
On a new system or where the private sector is providing services after completion of construction, such as maintenance or operations, the relevant project contracts should provide for a bedding-in period in the payment mechanism following the start of revenue service – that is, a period of time following revenue service where deductions are not applied in full. |
Transit Services Supply Services |
Transit Services will assess the opportunity for a period of extensive running of the fully integrated system prior to launch. This recommendation has been included in the contract for the Stage 2 Trillium Line extension Supply Services will update the P3 Procedures to include a bedding-in period as a consideration. |
In Progress Supply Services will update the P3 Policy by the end of Q3 2023 |
41 |
The relevant project contracts should provide for the early involvement of anyone engaged in public service (revenue service), prior to handover, to ensure that they are fully informed about the infrastructure and its maintenance needs, and fully trained to perform their respective roles. This early involvement should include, where possible, shadowing workers during construction and manufacturing. |
Transit Services |
Transit Services will ensure that early engagement of operations and maintenance are prioritized for Stage 2. A number of contract mechanisms are in place to deal with the handovers; however, early access for the maintainer and a clear handover process will be critical at this juncture. For the Stage 2 Trillium Line, a number of project staff who are experienced with the design and construction will transition to the maintenance team. Additionally, the maintainer has been able to recruit a number of key technicians from the original Trillium Line service to provide vehicle maintenance services. For the Stage 2 Confederation Line, the existing maintainer will grow their team over the coming years to accommodate the growth in maintenance obligations. Steps are being taken now to plan for this early familiarization and training. Early opportunities for handover of facilities will also enable the operators and maintainers to be fully informed about the infrastructure. |
Complete |
42 |
The handover process between entities responsible for the construction stage of the project and those responsible for the operations and maintenance stage needs to be organized and clearly and formally defined. Careful attention should be given to the transfer of responsibilities and information from the constructor to the maintainer, and the various criteria for handover should be explicitly set out, and cover both maintenance manuals and historical maintenance documentation. |
Transit Services |
Transit Services will ensure that early engagement of operations and maintenance are prioritized for Stage 2. For the Trillium Line extension, TNEXT is solely responsible for maintenance services and has begun the process for handover from its construction team. For the Confederation Line extension, agreements are in place between the design-build team and the maintainer to ensure that transfer of responsibilities is clear. |
In Progress |
43 |
Project agreements should provide for different performance requirements for differing weather conditions. An LRT system cannot be expected to perform in the same way in any and all weather conditions. |
Transit Services |
Design changes applied to Stage 1 have been incorporated into Stage 2. Currently, Transit Services does make operational adjustments due to weather conditions. |
In Progress |
44 |
Project agreements should be structured to account for potential expansions or additions to the project, and provide a reasonable and realistic process to make sure the expansion does not undermine the balance of power between the parties already involved in the contract. This may include provisions that set the lenders’ consent to eventual system extensions. |
Transit Services Supply Services |
Supply Services will update the P3 Policy to note that in drafting Project Agreements, consideration should be given to whether the project may expand at some point in the future, and how that would be accommodated. A similar update would likely need to be made the Project Management Policy to account for non-P3 projects. |
In Progress |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
45 |
Regardless of the project delivery model chosen, collaboration should be at the heart of the relationship between the public entity and private-sector partner(s). |
Transit Services |
The January 2023 Global Settlement between the City of Ottawa and RTG addressed, as a key priority, the relationship and collaboration between the two parties to improve service. |
Complete |
46 |
All private-sector stakeholders should be required to acknowledge that they are working in the public interest. The public interest should be a core organizational principle that informs all steps taken on a project. |
Transit Services |
The January 2023 Global Settlement between the City of Ottawa and RTG addressed, as a key priority, the relationship and collaboration between the two parties to improve service. |
Complete |
47 |
All stakeholders, including suppliers, operators, and maintainers, should be involved as early as is practicable in the project (including, where possible, procurement) with a view to aligning the parties’ incentives to collaborate and to avoid conflicts in stakeholder objectives. |
Finance and Corporate Services |
The Finance and Corporate Services Department is reviewing the impact of this recommendation on the Business Case and Project Management Policy and the Enterprise Risk Management Policy. Where changes are required, staff will update the language of these policies and link to department-specific procedures for project execution. This review is part of a review of the Business Case and Project Management Policy that is already underway, which is expected to be concluded by Q4 2023. Any policy or procedure changes will be communicated to City staff. |
In Progress Finance and Corporate Services expects to update the Business Case and Project Management Policy by Q4 2023. |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
48 |
The entity charged with overseeing a project must ensure that its various subcontracts align and are consistent with each other, and that no gaps in project obligations or deliverables are left unaddressed. |
Transit Services Supply Services |
Transit Services will ensure that agreements are fully aligned. During the inquiry there was information raised which suggested a misalignment between subcontracts at the design-build level, and the City will assess. |
Complete |
49 |
The contractor should involve or consult with the necessary experts to ensure that the plans, including timelines and scope of responsibilities for the subcontracted work, are logical and realistic. |
Transit Services Supply Services |
Transit Services will ensure that agreements are fully aligned. During the inquiry there was information raised which suggested a misalignment between subcontracts at the design-build level, and the City will assess. |
Complete |
50 |
The contractor needs to pay early attention to systems integration. A qualified systems integrator should be involved in the project from the design phase through to construction and manufacturing. In particular, a systems integrator should be a required member of the bid team and be involved in key contractual negotiations. |
Transit Services |
The approach to integration has been changed in Stage 2 where staff rely on European standards, amongst others, to ensure that a rigorous process is in place to deal with systems integration and integration testing more broadly. As noted previously, a new Systems Integration Verifier role has been added to Stage 2 that will work to ensure the integration of the headend equipment at the TOCC and the field equipment is properly completed. This role is intended to review integration issues between the City’s delivery scope in the control centre and Project Co’s delivery scope in the field; the role does not consider other integration that is otherwise covered by the project delivery teams. In instances where the integration work is fully within Project Co’s remit, systems integration will be led by the Project Co’s Systems Integration Manager. |
Complete |
51 |
Systems integration should be overseen by a single entity, and not split between different subcontractors or entities. Responsibility for this work should be clearly defined. |
Transit Services |
The approach to integration has been changed in Stage 2 where staff rely on European standards, amongst others, to ensure that a rigorous process is in place to deal with systems integration and integration testing more broadly. As noted previously, a new Systems Integration Verifier role has been added to Stage 2 that will work to ensure the integration of the headend equipment at the TOCC and the field equipment is properly completed. This role is intended to review integration issues between the City’s delivery scope in the control centre and Project Co’s delivery scope in the field; the role does not consider other integration that is otherwise covered by the project delivery teams. In instances where the integration work is fully within Project Co’s remit, systems integration will be led by the Project Co’s Systems Integration Manager. |
Complete |
52 |
For major infrastructure projects with complex components like LRVs, steps should be taken to ensure that prototypes and component designs are finalized early enough in the project to allow for best practices in confirming the prototype (for example, validation testing) before starting serial manufacturing. |
Transit Services |
The approach to integration testing has changed in Stage 2 to require the application of European standards, amongst others, to ensure that a rigorous process is in place to deal with systems integration and integration testing more broadly. |
Complete |
53 |
The contractor should maintain a consolidated program schedule incorporating all project activities. These scheduled activities need to align. All stakeholders should have access to this consolidated program schedule. |
Transit Services |
The Project Agreements set out clear requirements for schedule reporting and provision of an accurate consolidated schedule. |
Complete |
54 |
The consolidated program schedule incorporating everyone’s activities should be updated to reflect changes to the schedule as the work progresses. The consolidated schedule should remain logical, realistic, and reasonable. |
Transit Services |
The Project Agreements set out clear requirements for schedule reporting and provision of an accurate consolidated schedule. |
Complete |
55 |
Material changes in the construction or manufacturing plans should be communicated to those stakeholders who may be impacted by the change. Ideally, these partners will be consulted in advance of a material change being made to the project. |
Transit Services |
Improvements to the monitoring of contingency fund spending were brought forward for Stage 2 Light Rail in response to the findings of the Auditor General in the Audit of Stage 2 LRT Contingency Funding. This is an ongoing process where material changes to the design are brought forward for review. |
Complete |
56 |
The contractor must keep its public-sector client apprised of realistic timelines for the completion of the project. |
Transit Services |
The Project Agreements set out clear requirements for schedule reporting and provision of an accurate consolidated schedule. |
Complete |
57 |
The public-sector client must show leadership and approach the project with a view to delivering a quality end product. It must act co-operatively and flexibly in a manner consistent with the public interest. The client must also be reasonable and respond fairly if challenges arise that may result in project delays. This includes enabling the ability to pause and slowly replan the work as necessary. The public-sector client must also be realistic and not require the submission of schedule updates indicating on-time completion, unless on-time completion is realistic in all the circumstances. |
Transit Services |
Transit Services has taken a collaborative approach to management of the project schedules during Stage 2. We have openly and transparently reported on project schedules with the public and have worked closely with the contractors to address and deal with delays. We are working closely with the contract teams in a collaborative and open manner while still preserving our contractual rights. |
Complete |
58 |
Public entities and private-sector service providers working on complex infrastructure projects should continually foster a culture of early reporting of issues, challenges, and mistakes. |
Transit Services |
Transit Services has worked diligently to foster a culture of continuous improvement and early reporting of challenges. The January 2023 Global Settlement between the City of Ottawa and RTG addressed, as a key priority, the relationship and collaboration between the two parties. |
Complete |
59 |
There must be an appropriate process to honestly identify and communicate reliability and safety issues, not only within the project stakeholder group, but also within the public entity and to the public. |
Transit Services |
Transit Services has publicly committed to providing daily updates during the Trial Running period in order to openly and directly communicate any reliability issues and safety issues to the public. |
Complete |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
60 |
The decision-making and information sharing by city staff about project implementation must always accord with the terms of any delegation of authority and other governing council resolutions. |
Office of the City Clerk Legal Services |
Subsection 270(1)(6) of the Municipal Act, 2001 (the Act) provides that a municipality shall adopt and maintain policies with respect to the “delegation of its powers and duties.” The Council-approved Delegation of Powers Policy fulfills the requirements of the Act and provides that, “Every delegation of a power or duty of Council shall be accompanied by a corresponding accountability and transparency mechanism.” The policy further requires that enhanced accountability and transparency mechanisms, including consultation and reporting over and above what may be required under the Delegation of Authority By-law, are “formally considered and assessed in potentially high-profile or sensitive matters.” The accountability and transparency mechanism generally includes a “reporting out” requirement that may specify the frequency and means by which Council is provided with information about the exercise of delegated authority. The reporting out requirement may be set out in items such as the Delegation of Authority By-law, a staff report recommendation, or a Council resolution. As part of the 2022-2026 Council Governance Review report, the Office of the City Clerk recommended that the Council and Committee report template be amended to include a new “Delegation of Authority Implications” section. The Implications section summarizes the delegated authority being requested, or where existing authority is being exercised. In addition, staff are required to specify how the exercise of delegated authority will be reported out, in accordance with the Delegation of Powers Policy. Legal Services is undertaking a review of the Employee Code of Conduct, with updates anticipated for Q1 of 2024. The revised Code will reinforce staff’s obligations with respect to transparency and accountability. Related guidance documents will refer to the requirement for staff to adhere to applicable policies and by-laws, including the Delegation of Powers Policy and the Delegation of Authority By-law. |
Complete |
61 |
The participation of any elected officials in project decision-making must be done transparently, and in accordance with the governance mechanisms established by council, including any delegation of authority. |
Office of the City Clerk |
Section 5 of the Municipal Act, 2001 (the Act) provides that, “The powers of the municipality shall be exercised by its council,” and that a municipal power “… shall be exercised by by-law unless the municipality is specifically authorized to do otherwise.” In accordance with the statute, Council as a whole approves decisions and resolutions on all matters, including project decision-making, during public meetings held pursuant to the Act. Council’s decisions and resolutions are encompassed in the Confirmation By-law which, enacted at the end of every Council meeting, provides that every Council decision is made by by-law. Existing governance mechanisms such as the Council-approved Accountability and Transparency Policy may apply to the participation of Members in project decision-making. At its public meetings, Council may also establish project-specific governance mechanisms that provide for specific delegations of authority, along with related accountability and transparency mechanisms such as “reporting out” requirements. The conduct of Members who participate in decision-making must adhere to any requirements set out in the Code of Conduct for Members of Council, including obligations with respect to transparency. While the role of Council as a whole is outlined above, it should be noted the Mayor has authority to “exercise the powers of the municipality to direct municipal employees” regarding certain matters under Bill 3, the Strong Mayors, Building Homes Act, 2022, and its related Regulations, which came into force on November 23, 2022. That said, any such direction issued by the Mayor is subject to statutory requirements with respect to transparency, including the requirement that the direction be issued in writing and made available to Council and the public. Regular reviews of Council’s governance mechanisms are conducted twice per term of Council, and include matters relating to delegation of authority, transparency and accountability. Members of Council will continue to receive orientation and training from the Office of the City Clerk regarding the role of Council and delegated authority in project decision-making. The Integrity Commissioner will continue to provide Members with information regarding their obligations under the Code of Conduct for Members of Council. |
Complete |
62 |
Council and any other person or entity (such as the City of Ottawa’s Transit Commission) charged with project oversight must be able to exercise meaningful oversight of critical decisions made by city staff. This includes by receiving timely updates from staff relating to system performance, testing, and modifications to safety and reliability criteria. Where projects encounter serious difficulty and decisions must be made that will have a significant impact on the public interest, council must be kept fully informed so that it has the opportunity to act. |
City Manager’s Office |
City Council recently approved resolutions and issued a direction relating to project oversight and delegated authority for Stage 1 and Stage 2 Light Rail Transit (LRT), and delegated authority more broadly, as follows: · On February 22, 2023, Council considered the matter of, “Motion – City Manager Delegated Authority on Amendments to the Stage 1 Light Rail Transit Project Agreement.” Council approved recommendations from the Light Rail Sub-Committee and directed the Interim City Manager “to bring forward to Council a report on the Delegated Authority which has been delegated to the Interim City Manager with respect to the Stage 1 and Stage 2 Project Agreements that would permit Council to receive a briefing on the current use and application of delegation of authority on Stage 1 and Stage 2 of the LRT.”
Council further approved that the Light Rail Sub-Committee receive regular updates on the use of the delegated authority from the Interim City Manager with respect to Stage 1 and Stage 2 LRT Project Agreement amendments, and directed the Interim City Manager to bring forward to Council for approval any material amendments related to the Stage 1 and Stage 2 LRT Project Agreements. On December 7, 2022, Council issued a direction to the Interim City Manager “to bring forward a report summarizing the purpose and scope of all existing and requested Delegated Authority set out under each Schedule of the Delegation of Authority By-law to the Finance and Economic Development Committee [Finance and Corporate Services Committee] and City Council for consideration.” |
In Progress The Light Rail Sub-Committee and Council received the report on the City Manager’s Delegated Authority with Respect to Stage 1 and Stage 2 Light Rail (ACS2023-TSD-TS-0001) on March 29 and April 12 respectively. The City Manager’s Office expects to bring forward a report summarizing the purpose and scope of all authority set out under each schedule of the Delegation of Authority By-law in Q2 2023. |
63 |
All relevant project agreements and subcontracts, as well as any modifications made to them, should be available for review by city council, unless there is a compelling reason that it should not be made available. The burden of establishing a “compelling reason” should be placed upon the party asserting that the contract should not be available. |
Office of the City Clerk Transit Services |
The City must adhere to statutory provisions that may apply to the disclosure of certain types of information under legislation such as the Municipal Freedom of Information and Protection of Privacy Act (MFIPPA). Furthermore, as disclosing certain contractual provisions might prejudice the City’s legal and other interests, the City may need to place limits on the internal use and external disclosure of information. Such limits may include ensuring that the information is only used for certain purposes and is safeguarded in a secure place at all times. That said, in the absence of a compelling statutory reason that the information should not be made available, the following approaches may be considered to provide Members with access to contract documentation that would not otherwise be made public:
· Council may elect to establish, by way of resolution, a formal process for accessing the information. · Council and/or a Standing Committee/Commission may elect to receive certain information in camera, in keeping with Subsection 239(2) of the Municipal Act, 2001. · Upon request from a Member, the relevant General Manager may provide an opportunity for the Member to review the documentation at a particular location by appointment, further to a review of the information sought and any applicable statutory and/or contractual provisions to ensure that the Member’s viewing complies with any legislative or contractual requirements. Such an opportunity to review the documentation would be provided to all Members if one request is granted. The City may also publicly disclose certain contracts and related information, subject to redactions to address the statutory and contractual requirements described above. As set out in the Accountability and Transparency Policy, the City proactively discloses executed contracts with a value of $100,000 or more that were not a result of public procurement, as well as contracts resulting from a public procurement exercise that are of significant public interest (such as the Confederation Line project). In addition, documentation may be routinely released by City departments under the Routine Disclosure and Active Dissemination Policy. |
Complete |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
64 |
The system’s safety requirements should be identified and detailed during the design phase of the project and referred to as the project evolves during construction. The contractor should design and build for safety from the outset to avoid a retroactive review of hazards and safety. It should aim to reduce the operational restrictions required to account for safety gaps upon completion of the project, to reduce risks of human error. |
Transit Services |
Stage 2 contractors have been following EN50126 and incorporating safety requirements into their design, construction and testing and commissioning verification and validation processes. Additionally, an Independent Safety Auditor role exists in Stage 2 and was engaged early in the design process to ensure that the contractors follow the complete program. The City has been deliberately more prescriptive in terms of the specific standards and approaches that are being used by the delivery teams in order to meet safety certification requirements and the subsequent review that is taken by the safety auditor on behalf of the project. |
Complete |
65 |
The safety management systems for those involved in various aspects of public service must be developed in collaboration with each other and must be aligned. This alignment should be confirmed prior to the start of public service. The safety management systems should also be updated as appropriate. |
Transit Services |
Stage 2 will undergo a review of all administrative documentation. This review has been added to the Regulatory Compliance project within the Rail Operational Readiness program The Safety Management System (SMS) for TNEXT for the Trillium Line will be reviewed and confirmed to be in alignment with OC Transpo’s SMS for the Trillium Line. The SMS from RTM will be reviewed and confirmed to be in alignment with OC Transpo’s prior to the launch of the Confederation Line extensions. OC Transpo has two SMS documents due to the differences in the regulatory regimes and requirements between Trillium and Confederation lines. The SMS documents are reviewed and updated annually. |
In Progress |
66 |
An independent safety auditor should be engaged early on in the construction of complex infrastructure projects. |
Transit Services |
As noted in memos sent to Council in August 2022 and April 2023, SENER has been engaged as the Safety Auditor for all three Stage 2 extensions since Q3 of 2020. |
Complete |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
67 |
Maintenance needs to be performed by a permanent, skilled, and local workforce. Where this workforce does not exist, extensive training is required. This training should take place prior to the handover of the infrastructure. Experienced workers should be brought in for an extended period before the start of public service to assist with training, to provide work-shadow opportunities for inexperienced staff members, and to assist with the effective maintenance of the system until the permanent staff can maintain the infrastructure on their own. This assistance should continue as required after the start of public service. |
Transit Services |
TNEXT has retained experienced mechanics to support the Trillium Line, and TNEXT and RTM will provide documentation to the City for Stage 2 to satisfy these requirements: · A maintenance safety case which will include, among other things, organization, positions, numbers of staff · Will need to demonstrate maintainability and sustainability of the system · These will be reviewed by the City as well as the Safety Certification Team · The City’s oversight plans will provide continual oversight on TNEXT and RTM’s performance Transit Services acknowledges that as governments invest in infrastructure like light rail, local industries and expertise are encouraged to grow. |
In Progress |
68 |
Operations needs to be performed by a permanent, skilled, and local workforce. Where this workforce does not exist, extensive training is required to prepare the new operators to handle public service. This training should take place prior to the handover of the infrastructure. Experienced operators should be brought in for an extended period of time before the start of public service to assist with training, to provide work-shadow opportunities for inexperienced staff members, and to assist with the effective operations of the system until the permanent staff can operate the system on their own. This assistance should continue as required after the start of public service. A new operator and maintainer must be provided with coordinated opportunities to work and train together on the full system during the pre-launch bedding-in period. |
Transit Services |
Stage 2 will have opportunities for shadowing and integration with experienced staff. During training of City Diesel Rail Controllers, TNEXT will provide oversight for all on the job training by experienced rail controller personnel. The City is reviewing the opportunity to retain these personnel to provide additional support during the initial period of passenger service. In addition, Transit Services has experienced train operators and supervisors who will be supporting Trillium Line operations. Further, the Confederation Line is an extension of an existing operation and is therefore supported by staff with multiple years of experience. |
In Progress |
69 |
Train operators should be trained on situational awareness. With trains that are automatically controlled, the operator should be trained to have greater awareness of the various surroundings around the train. The training should also address the need to observe and report any issues that arise during their operation of the train. |
Transit Services |
As part of the ongoing enhancements to the rail curriculum, changes are routinely made to ensure that staff are operating as safely as possible. The main curriculum for Line 1 includes training that speaks to and tests situational awareness throughout the course. All front-line rail staff were required to complete a full day refresher training on situational awareness in 2022. In addition to initial training, Rail Operations performs drills throughout the year, and conducts exercises and compliance tests based on a number of situations that not only assess employees’ compliance with existing operating procedures, but also serve to assist in the identification of gaps and areas for improvement. |
Complete |
70 |
Upon the system entering public service, the maintenance contractor must have adequate resources to meet the actual needs of the system, including accommodating any outstanding retrofit work. |
Transit Services |
Transit Services has been working with TNEXT to identify the level of resources to meet the needs of the Trillium Line Service and to minimize the volume of retrofits that could be required during service. |
In Progress |
71 |
On a new system or where the maintainers are new to the system, the public entity must allow for a learning curve and avoid putting undue pressure on the maintainers by, for example, generating unnecessary or overly voluminous work orders for the purpose of “testing” the system. |
Transit Services |
Transit Services will work with RTG and TNEXT as substantial completion approaches on the three Stage 2 extensions to ensure there is a clear understanding between all parties as to which items will be managed under the Minor Deficiencies List and which will be managed as work orders following Substantial Completion. |
In Progress |
72 |
The public entity should consider putting maintenance and operations under the same “umbrella” – that is, have them be carried out by the same stakeholder – as this may allow for better coordination of the two functions and better co-operation between all parties. If maintenance and operations are delivered by two separate entities, they must devise processes that help ensure co-operation and coordination, as these are key to reliable service. These processes should be revisited and adjusted whenever necessary to respond to the realities of operating and maintaining the infrastructure. |
Transit Services |
Transit Services will review the protocols in place to ensure alignment with the recommendation to ensure better cooperation with RTM and for Stage 2 for Line 1 and TNext for Line 2, in particular, governance documentation to help set the parameters around the relationship between the operator and maintainer. City staff conduct daily and monthly maintenance and engineering meetings with RTM to ensure cooperation and coordination as well as operational debriefs and joint coordination around severe weather events. These processes will also be implemented with TNext for Line 2. |
In Progress |
73 |
Maintenance and operating procedures and protocols must clearly set out the scope of work and responsibilities for the maintainers and operators, and how their activities are to be coordinated. These procedures and protocols must be prepared in advance of system handover to allow adequate time for training the maintainers and operators on them, and must enable direct communication between the operators and the maintainers of the system. |
Transit Services |
Transit Services will ensure that lessons learned from the launch of Stage 1 will be incorporated to clarify procedures and protocols for Stage 2. As part of the launch of Line 2, troubleshooting and interpretation guides will be prepared in advance with the involvement of all parties. Validation of the procedures and protocols in place occurs with the acceptance of the Maintenance Safety Case and the Operators’ Safety Case, which will occur in advance of the system handover. These protocols, procedures and operational guides will be incorporated into the training plans for operational staff and jointly developed and updated in partnership with RTM and TNext. |
In Progress |
74 |
There must be transparency between operators and maintainers regarding the state of the system, the work to be done, how that work will be approached, and what work has been completed. It is also imperative that there be transparency between the operator and maintainer when it comes to incidents on the system or infrastructure. For instance, the maintainer should be able to access operator records to investigate incidents on the line or to improve its processes and procedures. |
Transit Services |
Transit Services management agree and will seek cooperation from RTG in the accurate and timely reporting of issues affecting the reliability of the system, for instance, the Failure Reporting and Corrective Action (FRACA) system. Transit Services will work with RTG to establish a charter of shared commitments, based on these recommendations, to increase good will and transparency between the parties. RTG currently maintains good tracking systems for light rail vehicles. Transit Services will work with RTG and its subcontractors to encourage the expansion of this level of monitoring and transparency across the whole of the system. |
In Progress |
75 |
Transit operations and maintenance plans require regular reviews / ongoing monitoring and forecasting of human resource needs, to ensure that requisite resources are available as needed. |
Transit Services |
Transit Services will request plans and documentation so as to exercise appropriate oversight over RTM/Alstom staffing projections. Staff have opportunities to discuss staffing and other resource needs as part of the regular meetings with the maintainer. OC Transpo is carefully reviewing its own staffing projections to ensure that staff are properly onboarded and trained to support the handover of Stage 2. TNEXT and RTM will provide documentation to the City for Stage 2 to satisfy these requirements: · A maintenance safety case which will include, among other things, organization, positions, numbers of staff · Will need to demonstrate maintainability and sustainability of the system · These will be reviewed by the City as well as the Safety Certification Team · The City’s oversight plans will provide continual oversight on TNEXT and RTM’s performance |
In Progress |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
76 |
Staff of the public entity and the private-sector service providers must ensure that council (or such persons or entity responsible for project oversight) is provided with timely, complete, and accurate information about the infrastructure to allow for effective and transparent oversight. In providing this information, stakeholders must be mindful that they are serving the public and strive to maintain and bolster the public’s trust. |
Transit Services |
City Council has created a new Light Rail Sub-Committee specifically to provide oversight and receive regular reports regarding non-operational light rail issues. Transit Services staff will continue to provide regular, transparent reports to the Light Rail Sub-Committee and the Transit Commission Transit Services will seek assurances from RTM that they will provide timely and accurate information for the purposes of informing Council. |
In Progress |
77 |
Maintenance work orders should be fairly and appropriately classified to avoid disputes and ensure efficient operation of the system. Work order systems should clearly define different categories of work to avoid unnecessary disputes and overreach. |
Transit Services |
Negotiations with RTG are underway to enable the incorporation of lessons learned from Stage 1 into an interpretation guide to clarify procedures and protocols for Stage 2, that will be reviewed and updated regularly. |
In Progress |
78 |
The public entity should not overload the maintainer with work orders and should avoid entering batch orders where response times need to be met, in particular at inconvenient hours of the day, where avoidable. |
Transit Services |
Work is underway to improve the process and options have been explored for entering and tracking work orders to ensure proper pacing of work orders. Improvements have been made to reduce incidents of batch orders, for example offering RTG representatives the opportunity to join City staff on inspections. |
In Progress |
79 |
Deductions for poor maintenance performance must be fair and not overly punitive, and they must be applied fairly, reasonably, and with a view to the public interest in the long-term success of the project. |
Transit Services |
The Council-approved January 2023 Global Settlement between the City of Ottawa and RTG addressed this recommendation. |
Complete |
80 |
There should be timely and proper responses to problems related to maintenance and operations by all parties once they arise. The safety and needs of the public should be prioritized. |
Transit Services |
Transit Services has strong plans and protocols protecting the safety of the public, such as suspension of service and the implementation of R1 service to meet the needs of transit customers. RTG comment: User and system safety is paramount and the priority factor driving all operational decisions. RTG, through its subcontractor RTM, maintains an operational center at 805 Belfast which provides 24/7 coverage for the full system and yard operations. All problems are reported to the operational centre which ensures the required response is properly planned, taking into account service requirements and other priorities. |
Complete |
81 |
To minimize disputes and delays in resolving issues, it is important to clearly define the distinction between issues relating to maintenance and those that may be covered by the warranty of the constructor, as well as who bears responsibility for each. |
Transit Services |
Transit Services will work with RTG and TNEXT as substantial completion approaches on the three Stage 2 extensions to ensure there is a clear understanding between all parties as to which items will be managed under the Minor Deficiencies List and which will be managed as work orders following Substantial Completion. RTG comment: Maintenance is undertaken in accordance with preventative maintenance programs, and, where appropriate or where required, corrective maintenance is undertaken. This ensures that all issues are addressed as required regardless of whether covered by a warranty. This applies equally to both infrastructure, where the initial two-year infrastructure warranty period has lapsed, and to vehicles. To ensure that disputes and delays are minimized with the addition of stage 2, robust warranty protocols are being discussed and will be implemented. |
In Progress |
82 |
The constructor should be required to make an objective assessment of the anticipated retrofit work and scale the resources that it will make available post-handover to match that assessment. |
Transit Services |
Transit Services will seek assurances, work collaboratively, and exercise appropriate oversight to ensure this assessment takes place. RTG comment: The actual requirements for retrofit works to the vehicle is well-documented and informed from the lessons learned over the past 3.5 years of service. Recent improvements to vehicle reliability, the commissioning of additional stage 2 vehicles and increased staffing will expedite the implementation of the vehicle retrofit plan with minimal impact on day-to-day operations. |
In Progress |
83 |
It is critical that the timely and proper completion of maintenance activities be prioritized, including proactive and preventive maintenance. |
Transit Services |
Transit Services will work with RTM to ensure that they are prioritizing and reporting back effectively and transparently. RTG comment: Maintenance is undertaken in accordance with a preventative maintenance program. Timely completion of maintenance activities is monitored and audited on an ongoing basis both internally and externally. The Maintenance Contractor as well as the Maintenance Subcontractor are revising the current concession management process to ensure that any maintenance schedule changes are justified. Maintenance and warranty tasks have been and will continue to be completed by separate teams to ensure that both are correctly and timeously addressed. |
In Progress |
84 |
The party or parties involved in providing maintenance must have effective and robust quality control measures in place, including ensuring that work is performed in an orderly way, consistently documenting the completed steps, and having proper checklists and record keeping for the assembly and repair of safety-critical parts. |
Transit Services |
Following the August 2021 derailment, RTM undertook a substantial change in their quality control processes. This is part of the work that was completed to allow the safe return to service. TRA was engaged to provide independent and detailed oversight over this process. The continued exercise of oversight over RTM’s operations to ensure ongoing compliance will be incorporated into the Annual Line 1 Oversight Plan developed by Transit Engineering Services and Safety, Regulatory, Training & Development. RTG comment: The Maintenance Contractor conducts regular monthly audits on the Maintenance Subcontractor, these include audits of its (i) maintenance and rehabilitation scope, (ii) health, safety and environment, (iii) support processes and operations as well as (iv) its quality management system. Findings from these audits are used to continuously improve processes, specifically the Safety Management System which is enhanced on an ongoing basis. |
Complete |
85 |
Where avoidable, safety-critical maintenance should not be performed over two different shifts. It should also require a supervisory or quality control sign-off to ensure that work has been completed to the proper standard. |
Transit Services |
Transit Services will continue to exercise oversight over RTG’s quality assurance and quality control processes to ensure the implementation of this recommendation. RTG comment: Agreed, the performance of safety critical maintenance is generally not performed over two shifts. If, however, this cannot be avoided, the work is halted at an appropriate point in the activity and proper handover is conducted between the two shifts. These handover processes have been strengthened and handover oversight is provided by the quality control function. |
In Progress |
86 |
There should be a process that enables individual maintainers and operators to raise issues they observe on the system that require improvement or fixes, to help identify issues early on and ensure the system is as good as it can be. |
Transit Services |
Transit Services conducts daily and weekly meetings with the maintainers and is in regular contact and open to suggestions. There are processes through the SMS and the Confederation Line Safety Committee with the City and its maintainer to raise safety concerns and/or issues. OC Transpo staff working on the line and in the TOCC are trained and expected to report any unusual or abnormal activity / behavior to RTM whether it be vehicle, station and infrastructure or system related. OC Transpo tracks all information provided to the maintainer for tracking, trending and for follow-up where required, including tracking of corrective actions. RTG comment: The Maintainer's Asset Management System, IMIRS, has this functionality; it allows maintainers and operators to raise issues observed on the system through the opening of a work order. The respective work order, depending on its severity, is prioritized to ensure timely response and rectification, failing which, financial penalties are imposed on the Maintenance Contractor. |
Complete |
87 |
The province should implement a system for major infrastructure projects that gives legal protection to whistleblowers who bring forward concerns. Consideration should be given to extending legislation for whistleblower programs to municipalities more broadly. |
Government of Ontario |
N/A |
For the Provincial Government’s consideration |
# | Recommendation | Lead Department(s) | Actions to address the recommendation | Status and timelines for completion |
---|---|---|---|---|
88 |
Work undertaken to strengthen the City’s oversight framework should continue, including assessing OC Transpo’s oversight and monitoring programs and making any improvements identified to ensure safety and reliability of the system. |
Transit Services |
Transit Services’ work is underway and ongoing with input from TRA. There is an annual review of the OC Transpo’s Line 1 Oversight Plan and associated activities (Engineering & Safety, Regulatory, Training & Development), in addition to ongoing monitoring and oversight conducted by the RMCO. TRA’s review of the oversight plan is part of our commitment to continuous improvement and applies an additional safety lens. Other experts such as STV are providing oversight and external assessments. |
In Progress |
89 |
Following incidents on the system, OLRT1 parties should continue to hold debrief meetings with all stakeholders present, in order to identify lessons learned and make improvements going forward. |
Transit Services |
Transit Services’ SMS and standard operating procedures include a requirement to conduct debrief meetings with stakeholders after incidents on the system. Staff will continue to hold debrief meetings with stakeholders. RTG comment: Several meetings are held with City representatives on an ongoing basis – these include: daily meetings, a bi-weekly meeting, weekly meetings and a monthly meeting. These meetings are in addition to any ad-hoc meetings requested by any of the project stakeholders to make ongoing improvements. |
Complete |
90 |
A partnership approach should be adopted during the operations and maintenance phase and to address issues that arise on the system. |
Transit Services |
Partnership was the main theme RTG emphasized to the Commissioner as one of the prevalent lessons learned from recent years. The City and RTG acknowledge the evolution of the parties’ approach to the partnership, leading to the recent resolution of several issues. Partnership requires ongoing dialogue and common objectives. While the parties’ relationship continues to evolve, both sides recognize that the sustainability of Ottawa’s rail system will depend on a day-to-day commitment to transparency, respect and fairness. Transit Services and RTG have undertaken a partnership exercise and established a charter of shared values to guide discussions throughout the future of the maintenance period. |
In Progress |
91 |
Outstanding payment disputes between the City and RTG should be resolved at the earliest opportunity, in particular related to the City’s approach to issuing and classifying work orders, and the City’s administration of the payment mechanism (the City’s carrying forward of deductions incurred in a previous month to the next payment period, and the City’s interpretation of the impact of the delayed Revenue Service Availability date on the maintenance payment schedule). |
Transit Services |
The Council-approved January 2023 Global Settlement between the City of Ottawa and RTG addressed this recommendation. |
Complete |
92 |
If RTG continues to be responsible for maintenance during the remainder of the maintenance term, RTG and the City, as well as RTM and Alstom Maintenance, should make efforts to repair their relationships and work together better for the greater good of the OLRT1 project. |
Transit Services |
The City, RTG and its subcontractors are committed to the success of the OLRT project and are committed to working collaboratively together for the remainder of the Maintenance Term. All parties have been making significant headway towards working collaboratively at resolving issues. Over this period, RTG and its subcontractors have been transparent on all ongoing issues allowing City staff real-time access to information. The parties are committed to working to find an appropriate balance between monitoring and RTG’s ability to efficiently carry out day-to-day activities. RTG and the City share the same objectives and expect the partnership to continue to evolve, with the goal of shifting from ongoing monitoring to collaborative oversight. |
Complete |
93 |
If not yet complete, an engineering assessment of the appropriate rail neutral temperature for the OLRT1 should be completed, and the rail neutral temperature adjusted accordingly, so that the track buckling issues can be mitigated for the long term. |
Transit Services |
Transit Services acknowledges that the maintainer has been actively undertaking various works on the system (cutting/welding, ballast work, lateral anchors, and temperature testing) to improve the performance of the track in order to mitigate buckling issues. A Rail Neutral Temperature Report will be updated in summer 2023 based on additional measurements. RTG comment: This engineering assessment is ongoing and should be completed in the coming months. Additional testing has been scheduled to take place in May 2023, weather permitting. |
In Progress |
94 |
Alstom should continue its preventive maintenance of the line inductors, including checking them before and after every winter for any buildup of contaminants, and cleaning them as required. |
Transit Services |
Transit Services staff will continue to work with Alstom to ensure that this preventative maintenance takes place. RTG comment: The line inductors have undergone a modification program to restrict the ingress of water, salt, and debris into the enclosure. Critically, a batch problem with the inductors has been corrected the units have now been successfully used over multiple winters. RTG is also ensuring that the units are maintained in accordance with the preventative maintenance program. |
Complete |
95 |
Alstom should continue its regular inspections of the overhead catenary system to clean the parafils as required, or repair/replace them as necessary. |
Transit Services |
Transit Services staff will continue to work with Alstom to ensure that this preventative maintenance takes place. Locations with repeated failures will be reviewed and enhancements implemented as necessary to improve system reliability. RTG comment: The parafils are subject to regular inspection; this includes the six-month inspection, which is a detailed review of the major components of the OCS, including the parafils. The root cause of recent incidents affecting the parafils are being analyzed to assess whether the longevity of these assets can be enhanced. |
In Progress |
96 |
The City, RTG and its subcontractors, and Alstom must follow through on the outstanding investigations regarding the root cause of the August 8, 2021 derailment, act on the findings, and ensure that any root cause of this derailment is addressed. |
Transit Services |
Transit Services staff will work with RTG and its subcontractors on any requirements arising from the final root cause report. RTG comment: Alstom and RTG have appointed independent third parties to conduct thorough investigations regarding the root cause of the August 2021 derailment, these investigations are ongoing. Once complete, a consolidated report will be prepared detailing the conclusions reached and the proposed way forward. In the interim, various mitigation strategies have been put in place to ensure the safety and reliability of the system, in addition, the effectiveness of vibration monitoring is being investigated as a possible early detection mechanism. |
In Progress |
97 |
A permanent solution to the wheel/rail interface issues needs to be identified and implemented in a timely manner. This solution may involve using a different type of wheel, replacing the track or part of the track, additional track reprofiling, enhancing the axle design to withstand the forces coming from the track, or even modifying the track alignment to address the issue of sharp curves. A wheel/rail interaction study should be undertaken to determine the appropriate solution(s). All parties should work co-operatively to implement the solution(s). |
Transit Services |
Transit Services, RTG and its subcontractors conduct regular Wheel/Rail Working group meetings as part of the resolution of this recommendation. RTG comment: A permanent solution to the wheel/rail interface issues is being investigated. As part of the investigation, the National Research Council Canada (NRC) prepared a preliminary report examining the initial wheel/rail interaction and identifying detrimental characteristics (such as wear and rolling contact fatigue) in December 2021. A further report was prepared in March 2022 which went beyond the preliminary report, looking at the wear and surface damage trends of the wheels and rails. It also evaluated the current friction management practices to establish the cause for the most prevalent Confederation Line issues such as corrugation and wheel squealing. An optimized wheel/rail profile was also prepared by the NRC which remains part of the ongoing investigation in identifying a permanent solution. |
In Progress |
98 |
Transportation Resource Associates or another independent third-party expert should continue to monitor safety issues and remedial actions undertaken by the parties to ensure the continued safe operation of the OLRT1 system, pending a final resolution of the issues relating to the wheel/rail interface and the first derailment. This independent safety expert should report directly to Council or to the Transit Commission. |
Transit Services |
Transit Services will continue to utilize independent third-party expertise, as well as the additional oversight exercised through OC Transpo’s new centralized Transit Engineering Services service area. TRA continues to be engaged to monitor safety issues pending a final resolution of the wheel/rail interface. As mentioned in response to recommendation 88, there is an annual review of OC Transpo’s Line 1 Oversight Plan and associated activities, in addition to ongoing monitoring and oversight conducted by the RMCO. City Council has also created additional oversight through the creation of the new LRT sub-committee of Council. |
In Progress |
99 |
Pending the implementation of a permanent solution to the wheel/rail interface, and any other issue that may later be found to have contributed to the August 8, 2021 derailment, the City and RTG should continue implementing the current remedial measures intended to ensure the safe and reliable operation of the system, including any new measures that are deemed advisable as more becomes known about the root cause of the derailment and the wheel/rail interface more generally. These should include: a. Reducing rail corrugation through maintenance; b. Increasing track lubrication (greasing); c. Adjusting the speed profile (to lower the speed in some places, particularly along curves); and d. Modifying the wheel profile to better sustain the transversal forces coming from the track. |
Transit Services |
Transit Services is conducting weekly meetings with RTG and Alstom to track progress on this work. Additional oversight through TRA is integrated into this process. RTG comment: Corrugation is addressed through an annual grinding campaign, which was last conducted in August 2022 during the major maintenance shut down period. There are two types of lubrication (i) gauge face/flange lubrication and (ii) top of rail that are being assessed for effectiveness. Temporary Speed Restrictions are currently in place throughout the system. As discussed in recommendation 97, an optimized wheel to rail profile has been developed and is being investigated. |
In Progress |
100 |
RTM should implement the recommendation first made in the Track Safety Justification Report and the Operational Restrictions Document, and establish a wheel/rail working group to optimize the wheel and rail profiles, improve maintenance practices, monitor the wheel/rail interface, and minimize the impacts on the rail and vehicle components. In particular, the working group should focus on: a. Monitoring the rate of wear on the wheels through increased visual inspection or non-destructive testing; b. Increasing visual inspections of wear on the rail at all sharp curves to measure side wear rates; c. Using ultrasonic testing as well as visual inspections, and collecting related data; d. Monitoring the effectiveness of LRV-mounted lubricators to address locations with rail wear, and evaluating the possibility of installing rail-mounted or trackside lubricators and friction modifiers; e. Increasing the frequency of preventive rail grinding across the whole system to reduce the risk and growth of “rolling contact fatigue”; f. Measuring corrugation throughout the system to help identify where corrugation is forming and the growth rates, to inform the required frequency of proactive rail grinding; g. Reviewing the profile of the switch blade to reduce the rate of wear; and h. Identifying remedial actions that can be taken to prevent the deterioration of the rail and wheel components. |
Transit Services |
Transit Services will work collaboratively with RTG to support the implementation of this recommendation. RTG comment: Optimization of the wheel to rail profile is being investigated, please refer to recommendation 99 in this regard. In addition, several focus areas have been explored; these include ultrasonic and visual inspections as well as corrugation measurement conducted by Advanced Rail Management, and the ongoing testing of the effectiveness of wayside rail lubrication. Others, to the extent applicable, continue to be investigated. |
In Progress |
101 |
The operating profile should be adjusted as necessary to ensure the safety and reliability of the OLRT1 system by reducing stress on the vehicle components and avoiding excessive wear. Consideration should be given to reducing vehicle speeds, particularly along curves and to account for different climatic conditions. The parties should work collaboratively over the long term to agree on changes in the best interests of the transit riders and taxpayers. |
Transit Services |
Instrumented bogie testing will help to support the implementation of this recommendation. Based on the Instrumented Bogie testing of November 2022, RTM has recommended existing temporary speed reductions should remain. A comprehensive report that considers a number of factors that impact safety and reliability of the O-Train system is anticipated in Q2 2023. City staff will review the results of that report. RTG comment: As discussed at recommendation 99 above, Temporary Speed Restrictions have been implemented. In addition, Type 1 and 2 breaking has been proactively implemented to account for changing climatic conditions. Ongoing investigations are underway in collaboration with all stakeholders to find long-term sustainable solutions to enhance vehicle safety and reliability. |
In Progress |
102 |
Alstom should follow through with its plans to replace the spline axles on the LRVs following the problems with excessive wear to the splines that were identified in its presentation dated June 30, 2021. |
Transit Services |
Transit Services will support Alstom in completing this recommendation. A proactive axel replacement program is in place, based on measured wear and kilometres travelled.
RTG comment: Alstom, in conjunction with other project stakeholders, is actively involved developing recommendations for a sustainable solution for the Ottawa LRT, a recommendation which is currently being explored is the possible redesign of the spline. |
In Progress |
103 |
The parties should consider the use of a detection system as a potential remedial option for overheated roller bearings. |
Transit Services |
Transit Services is supporting Alstom’s pilot project that started in Q4 2022 to assess the effectiveness of utilising vibration monitoring “Smart Bugs.” Currently 40 axles over 4 LRVs are fitted with “Smart Bugs” and Alstom is monitoring vibrations from vehicles in service to detect a “signature” that would indicate a bearing condition below serviceability limits. Discussions are also underway with the National Research Council to determine the feasibility of undertaking a bench test to establish the “signature.” RTG comment: Vibration monitoring devices have been installed on pilot vehicles to assess whether vibration monitoring would be an effective early detection mechanism. In addition to this pilot project, Alstom, in conjunction with other project stakeholders, is actively involved developing further recommendations for a sustainable solution for the Ottawa LRT. |
In Progress |
As part of our standard practice, we notify the Transportation Safety Board of Canada (TSB) of any unforeseen occurrences on our transit system.